Free Practice Test

Free PMP Practice Test

10 scenario-based PMP practice questions covering agile, EVM calculations, Scrum, risk management, stakeholder engagement, and critical path. No signup required. See correct answers instantly.

10 Free PMP Practice Questions

Q1. A project manager is leading a software development project. The team has been using a waterfall approach but the client keeps requesting changes after each phase. What should the project manager recommend?Show answer
A) Reject all change requests until the project is complete to maintain schedule integrity
B) Transition to an agile or hybrid approach to accommodate evolving requirements
C) Escalate the client's change requests to the sponsor and pause the project
D) Issue a formal scope change notice and charge the client for each request

✓ Correct Answer: Transition to an agile or hybrid approach to accommodate evolving requirements

When requirements are volatile and the client is repeatedly requesting changes after phases, a predictive (waterfall) approach creates friction and rework. The PMI-preferred response is to evaluate whether an agile or hybrid approach better fits the project context — agile embraces change through short iterations, sprint reviews, and continuous customer collaboration. This is a core PMP concept: selecting the right life cycle for the project environment.

Q2. At the end of month 3, a project has a Planned Value (PV) of $120,000, an Earned Value (EV) of $90,000, and an Actual Cost (AC) of $110,000. What is the Cost Performance Index (CPI)?Show answer
A) 0.75
B) 0.82
C) 1.22
D) 1.33

✓ Correct Answer: 0.82

CPI = EV ÷ AC = $90,000 ÷ $110,000 = 0.818 ≈ 0.82. A CPI below 1.0 means the project is over budget — you are getting less than $1 of work for every $1 spent. The Schedule Performance Index (SPI) = EV ÷ PV = $90,000 ÷ $120,000 = 0.75, meaning the project is also behind schedule. Both metrics are unfavorable, signaling the need for corrective action.

Q3. In a Scrum framework, who is responsible for maximizing the value of the product and managing the Product Backlog?Show answer
A) The Scrum Master, who facilitates all backlog refinement sessions
B) The Development Team, who has the technical knowledge to prioritize work
C) The Product Owner, who represents the stakeholder interests
D) The Project Sponsor, who approves all backlog items before they enter a sprint

✓ Correct Answer: The Product Owner, who represents the stakeholder interests

In Scrum (per the Scrum Guide), the Product Owner is solely accountable for maximizing the value of the product and managing the Product Backlog — which includes ordering items, ensuring the backlog is transparent and clear, and making trade-off decisions. The Scrum Master serves the team by removing impediments and coaching Scrum practices. The Development Team is self-organizing and selects backlog items for each sprint based on capacity.

Q4. A project manager identifies a risk that has a 40% probability of occurring and would cost $50,000 if it did. What is the risk's Expected Monetary Value (EMV)?Show answer
A) -$50,000
B) -$20,000
C) $20,000
D) $50,000

✓ Correct Answer: -$20,000

EMV = Probability × Impact = 0.40 × (−$50,000) = −$20,000. Risk impacts are expressed as negative values (threats) or positive values (opportunities). EMV is used in decision tree analysis and contingency reserve calculations. A −$20,000 EMV means this risk contributes $20,000 to the project's contingency reserve calculation. The sign convention is critical on the PMP exam — threats are negative, opportunities are positive.

Q5. A key stakeholder who was not engaged early in the project is now opposing a critical deliverable. What is the BEST first action for the project manager?Show answer
A) Escalate the issue to the project sponsor and request that the stakeholder be overruled
B) Document the stakeholder's opposition in the issue log and continue the project
C) Meet with the stakeholder to understand their concerns and identify common ground
D) Issue a formal change request to revise the deliverable to satisfy the stakeholder

✓ Correct Answer: Meet with the stakeholder to understand their concerns and identify common ground

The PMI approach to stakeholder conflict is to engage proactively — understand their concerns first before escalating or making changes. Stakeholder engagement should begin early (stakeholder identification happens during project initiation) and continue throughout. Meeting to understand concerns aligns with the Stakeholder Engagement Plan and the principle of collaboration. Escalating immediately or issuing a change request without understanding the root concern would be premature.

Q6. The critical path of a project is the sequence of activities that:Show answer
A) Has the highest total cost and the most resource requirements
B) Has the longest duration and determines the shortest possible project completion date
C) Contains the activities most likely to be delayed based on historical data
D) Is identified by the project sponsor as the highest business priority

✓ Correct Answer: Has the longest duration and determines the shortest possible project completion date

The critical path is the longest path through the project network diagram, and it determines the minimum project duration — any delay on a critical path activity directly delays the project end date. Activities on the critical path have zero total float (or zero slack). There may be multiple critical paths. The critical path method (CPM) is a core scheduling technique tested heavily on the PMP.

Q7. During a sprint review, the stakeholder rejects a completed user story because it doesn't match their vision. What should have prevented this situation?Show answer
A) A more detailed project charter approved by all stakeholders at project initiation
B) A formal quality audit performed before each sprint review by the QA team
C) Ongoing stakeholder collaboration and clear acceptance criteria defined before sprint work begins
D) A risk register entry for 'stakeholder misalignment' with a mitigation plan

✓ Correct Answer: Ongoing stakeholder collaboration and clear acceptance criteria defined before sprint work begins

In agile, acceptance criteria are defined before a story enters the sprint (during backlog refinement). The Definition of Done (DoD) and story-level acceptance criteria ensure shared understanding between the team and stakeholders. The sprint review itself is a feedback mechanism — if stories are being rejected there, it signals a breakdown in collaboration or acceptance criteria clarity earlier in the process, not a problem with the review itself.

Q8. A team member raises a conflict with another team member in a meeting. As the project manager, which conflict resolution technique is MOST likely to produce a lasting solution?Show answer
A) Smoothing — acknowledge the conflict minimally and refocus the meeting on project work
B) Forcing — use your authority as PM to impose a decision immediately
C) Collaborating (Confronting) — openly address the conflict and work toward a mutually acceptable solution
D) Withdrawing — allow the team members to resolve it on their own without involvement

✓ Correct Answer: Collaborating (Confronting) — openly address the conflict and work toward a mutually acceptable solution

PMI's preferred conflict resolution technique is Collaborating (also called Confronting or Problem Solving) — it addresses the root cause of the conflict and seeks a win-win outcome. It produces the most durable resolution. Smoothing provides a temporary fix. Forcing may resolve it quickly but breeds resentment. Withdrawing avoids the issue entirely. The PMP exam consistently favors the collaborative approach as the 'best' first response to team conflict.

Q9. The Estimate at Completion (EAC) for a project with BAC = $500,000 and CPI = 0.80 is:Show answer
A) $400,000
B) $500,000
C) $600,000
D) $625,000

✓ Correct Answer: $625,000

EAC = BAC ÷ CPI = $500,000 ÷ 0.80 = $625,000. This formula assumes the current cost performance (CPI) will continue for the remainder of the project — the most common EAC formula on the PMP exam. A CPI of 0.80 means you are getting $0.80 of work for every $1 spent, so the project will cost 25% more than budgeted. The Estimate to Complete (ETC) = EAC − AC (actual cost to date).

Q10. A project manager is managing a project in a matrix organization. A functional manager keeps pulling team members off the project for other work. What is the BEST way for the project manager to handle this?Show answer
A) Formally escalate to the PMO and request that the functional manager be removed from the project
B) Meet with the functional manager to discuss resource availability and negotiate a shared schedule
C) Replace the team members with contractors to avoid the functional manager's interference
D) Document each instance in the issue log and raise it at the next project status meeting with the sponsor

✓ Correct Answer: Meet with the functional manager to discuss resource availability and negotiate a shared schedule

In a matrix organization, the project manager shares authority over resources with functional managers — this is a defining characteristic of the matrix structure. The correct response is to engage the functional manager directly to negotiate resource availability, understand their competing priorities, and reach a workable arrangement. Escalating immediately bypasses direct communication. Replacing with contractors is a disproportionate escalation. The PMI approach favors direct, proactive communication before escalation.

What Does the PMP Exam Cover?

The PMI PMP exam (180 questions, 230 minutes) is based on the Exam Content Outline (ECO) with three domains: People (42%), Process (50%), and Business Environment (8%). Approximately 50% of questions are agile or hybrid, 50% are predictive. The exam tests judgment in scenario-based situations — you must identify the PMI-preferred response, not just recall definitions. Key topic areas include: Earned Value Management (EVM) calculations (CPI, SPI, EAC, ETC), Scrum framework (roles, ceremonies, artifacts), risk identification and response strategies, stakeholder engagement, conflict resolution, critical path method (CPM), and change control processes.

How Hard Is the PMP Exam?

The PMP is one of the most challenging professional certifications — industry estimates suggest a 55–65% first-time pass rate for well-prepared candidates. The difficulty comes from the scenario-based format: questions present complex project situations and ask what you should do "next" or "first" — and multiple answers can seem plausible. The agile/hybrid content added to the current exam also catches experienced waterfall PMs off guard. Candidates typically need 150–250 hours of study over 2–4 months. Question drilling is more effective than reading the PMBOK cover-to-cover.

How to Study for the PMP Exam

  1. 1.Master EVM formulas coldCPI = EV/AC, SPI = EV/PV, EAC = BAC/CPI, ETC = EAC − AC, CV = EV − AC, SV = EV − PV. These appear on almost every PMP exam. Practice calculating them quickly — exam time pressure is real. Know what each index means qualitatively (CPI < 1 = over budget, SPI < 1 = behind schedule).
  2. 2.Understand agile deeply — not just terminology50% of the exam is agile/hybrid. You must understand when to use agile vs. predictive, how Scrum works (sprints, retrospectives, Product Owner vs. Scrum Master roles), Kanban WIP limits, and hybrid approaches. Read the Agile Practice Guide from PMI.
  3. 3.Learn the PMI mindset for scenario questionsPMI has a preferred response hierarchy: (1) communicate first, (2) understand root cause, (3) update plans/documents, (4) escalate only as a last resort. Questions that ask 'what should the PM do FIRST?' are testing this mindset. Direct communication beats escalation. Proactive beats reactive.
  4. 4.Drill risk management and stakeholder engagementRisk response strategies (avoid, transfer, mitigate, accept for threats; exploit, share, enhance, accept for opportunities) and stakeholder engagement levels (unaware → resistant → neutral → supportive → leading) appear frequently. Know the difference between qualitative and quantitative risk analysis.
  5. 5.Practice 200+ questions per week in the final monthReading alone won't pass the PMP. Use a question bank that mirrors the scenario-based format. Review every wrong answer in detail — understanding why an answer is wrong is more valuable than confirming why the right answer is right. Aim to pass practice tests at 75%+ before your exam date.

Want 1,000+ PMP Questions?

Get the Full PMP Prep App — Free to Start

1,000+ scenario-based PMP practice questions covering all three ECO domains. Agile, hybrid, and predictive. Built-in EVM Calculator. Full offline access. $49.99 one-time for lifetime access.

Download on theApp Store

Free to download · No credit card · iPhone & iPad