Skip to main content

LEED Green Associate Exam

Energy and Atmosphere Practice Questions

10 practice questions with detailed explanations — aligned to the LEED Green Associate Exam.

Master Energy and Atmosphere to boost your score on the LEED Green Associate Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 10 questions, review any that trip you up, and use the related topics below to round out your preparation.

  1. Q1.What does the Energy and Atmosphere (EA) Prerequisite: Fundamental Commissioning and Verification require?

    A.Achieving 10% better energy performance than ASHRAE 90.1
    B.Installing renewable energy on-site equal to 100% of building energy use
    C.Verifying that building energy-related systems are installed, calibrated, and performing according to design intent
    D.Conducting an energy audit every 3 years
    CVerifying that building energy-related systems are installed, calibrated, and performing according to design intent

    Explanation: Fundamental Commissioning requires a systematic process to verify that the Owner's Project Requirements (OPR) are met by the design and construction. It applies to HVAC, lighting controls, hot water, and renewable energy systems. Commissioning ensures systems perform as intended.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  2. Q2.Which ASHRAE standard is referenced in LEED's Energy and Atmosphere prerequisite for minimum energy performance?

    A.ASHRAE 55 (Thermal Comfort)
    B.ASHRAE 62.1 (Ventilation for Acceptable Indoor Air Quality)
    C.ASHRAE 90.1 (Energy Standard for Buildings)
    D.ASHRAE 189.1 (Green Buildings)
    CASHRAE 90.1 (Energy Standard for Buildings)

    Explanation: ASHRAE 90.1 (Energy Standard for Buildings Except Low-Rise Residential Buildings) is the baseline energy standard referenced in LEED. Projects must demonstrate a certain percentage improvement over this baseline. The referenced edition depends on the LEED version (v4 uses ASHRAE 90.1-2010).

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  3. Q3.What does the term 'energy use intensity' (EUI) measure?

    A.The peak electrical demand of a building in kilowatts
    B.Annual energy consumption per unit of gross floor area (kBtu/sf/year or kWh/m²/year)
    C.The ratio of renewable energy to total building energy use
    D.The efficiency rating of HVAC equipment
    BAnnual energy consumption per unit of gross floor area (kBtu/sf/year or kWh/m²/year)

    Explanation: Energy Use Intensity (EUI) = annual energy use ÷ gross floor area, expressed as kBtu/sq ft/year (IP) or kWh/m²/year (SI). Lower EUI indicates better energy performance. EUI is used to benchmark and compare building energy performance across building types and climates.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  4. Q4.What type of refrigerant is LEED's Enhanced Refrigerant Management credit designed to reduce or eliminate?

    A.CO₂ (carbon dioxide refrigerants)
    B.Refrigerants with high global warming potential (GWP) and/or ozone depletion potential (ODP)
    C.All synthetic refrigerants regardless of GWP or ODP
    D.Natural refrigerants such as ammonia and propane
    BRefrigerants with high global warming potential (GWP) and/or ozone depletion potential (ODP)

    Explanation: The LEED Enhanced Refrigerant Management credit aims to reduce or eliminate the use of refrigerants with high ozone depletion potential (ODP) and global warming potential (GWP), such as HCFCs and HFCs. Preferred refrigerants include low-GWP alternatives and natural refrigerants.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  5. Q5.A building generates more energy on-site than it consumes annually. What is this called?

    A.Net-zero water building
    B.Carbon-neutral building
    C.Net positive energy (or energy surplus) building
    D.Zero-emission building
    CNet positive energy (or energy surplus) building

    Explanation: A building that generates more energy than it consumes over the course of a year is net positive energy. A net-zero energy building produces exactly what it consumes. LEED's EA credit for renewable energy can award points for on-site or off-site renewable energy generation.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  6. Q6.ASHRAE 90.1 serves as the energy performance baseline for LEED EA credits. What does ASHRAE 90.1 establish?

    A.Minimum energy efficiency requirements for commercial buildings including HVAC, lighting, and building envelope
    B.Standards for air quality measurement in HVAC systems
    C.Fire safety requirements for electrical equipment
    D.Water heating efficiency standards only
    AMinimum energy efficiency requirements for commercial buildings including HVAC, lighting, and building envelope

    Explanation: ASHRAE 90.1 (Energy Standard for Sites and Buildings Except Low-Rise Residential Buildings) sets minimum energy performance requirements for commercial buildings. LEED requires buildings to meet or exceed ASHRAE 90.1 as a prerequisite, then awards credits for percentage improvement beyond the baseline.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  7. Q7.Which LEED EA strategy involves a systematic process to verify that building energy systems are installed and operating as designed?

    A.Fundamental Commissioning (Cx) — a LEED prerequisite
    B.Energy modeling
    C.Demand response
    D.Green power purchasing
    AFundamental Commissioning (Cx) — a LEED prerequisite

    Explanation: Commissioning (Cx) is a quality assurance process verifying that building systems (HVAC, lighting, controls, plumbing, etc.) are designed, installed, and operating per the Owner's Project Requirements (OPR). Fundamental Commissioning is a LEED prerequisite; Enhanced Commissioning earns additional credits.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  8. Q8.On-site renewable energy (e.g., solar PV) earns LEED EA credits by:

    A.Reducing the building's dependence on grid electricity and lowering greenhouse gas emissions
    B.Replacing the prerequisite requirement for ASHRAE 90.1 compliance
    C.Earning automatic LEED Platinum status if 100% of energy needs are met
    D.Only qualifying if the system includes battery storage
    AReducing the building's dependence on grid electricity and lowering greenhouse gas emissions

    Explanation: LEED's Renewable Energy Production credit awards points for producing renewable energy on-site (solar, wind, geothermal) proportional to total building energy consumption. Renewable energy reduces grid dependence and associated GHG emissions — a core LEED goal.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  9. Q9.Building energy modeling (BEM) in LEED is used to:

    A.Compare a proposed building's energy performance to a code-minimum baseline to quantify efficiency improvements
    B.Calculate the exact utility bills before the building is occupied
    C.Replace the commissioning process for large commercial projects
    D.Determine the LEED point total automatically based on energy use intensity
    ACompare a proposed building's energy performance to a code-minimum baseline to quantify efficiency improvements

    Explanation: Energy modeling simulates a building's annual energy performance using climate data, occupancy schedules, systems specifications, and envelope properties. It compares the proposed design to a code-minimum baseline (per ASHRAE 90.1 Appendix G) to quantify % energy savings for EA credits.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  10. Q10.Demand response programs earn LEED EA credits by:

    A.Enabling buildings to reduce electricity consumption during grid peak demand periods
    B.Installing smart meters to monitor real-time energy use
    C.Connecting the building to a renewable energy grid
    D.Achieving a minimum 50% reduction in annual energy consumption
    AEnabling buildings to reduce electricity consumption during grid peak demand periods

    Explanation: Demand response participation allows buildings to temporarily reduce electrical load (e.g., by adjusting HVAC setpoints or dimming lighting) when the grid is stressed. LEED rewards this for its grid reliability and emissions benefits — peak demand often relies on the most polluting 'peaker' power plants.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

More LEED Green Associate Exam Topics

Studying for the LEED Green Associate exam? Read more about LEED Green Associate