Skip to main content

OSHA 30-Hour Construction Exam

Cranes & Rigging Practice Questions

60 practice questions with detailed explanations — aligned to the OSHA 30-Hour Construction Exam.

  1. Q1.A crane's load chart provides information about:

    A.The crane's maintenance schedule
    B.The maximum rated capacity at various radii and boom lengths
    C.The crane's fuel consumption
    D.The operator's qualifications
    BThe maximum rated capacity at various radii and boom lengths

    Explanation: A load chart shows the maximum load that can be safely lifted at various boom lengths and radii. Operators must consult the load chart before each lift.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  2. Q2.Who is responsible for conducting a visual inspection of the crane before each shift?

    A.The project manager
    B.The competent person or qualified operator
    C.OSHA
    D.The crane manufacturer
    BThe competent person or qualified operator

    Explanation: A competent person must conduct a visual inspection of the crane before each shift. The operator is responsible for ensuring the crane is safe to operate.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  3. Q3.The minimum clearance distance between a crane/boom and overhead power lines up to 50kV is:

    A.5 feet
    B.10 feet
    C.15 feet
    D.20 feet
    D20 feet

    Explanation: For power lines up to 50kV, the minimum clearance distance for cranes is 20 feet during transit (or 10 feet during operation with specific safety measures). The table in 1926.1408 specifies the requirements.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  4. Q4.A crane operator must be:

    A.At least 21 years old
    B.Certified or qualified to operate the specific type of crane
    C.A licensed engineer
    D.An OSHA compliance officer
    BCertified or qualified to operate the specific type of crane

    Explanation: Crane operators must be certified by an accredited crane operator testing organization or qualified through the employer's evaluation program.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  5. Q5.What is the primary purpose of outriggers on a crane?

    A.To increase the crane's speed
    B.To provide additional stability and support during lifting operations
    C.To protect the tires
    D.To assist with steering
    BTo provide additional stability and support during lifting operations

    Explanation: Outriggers extend from the crane body and are set on pads to provide a wider, more stable base for lifting operations. They must be fully extended and set on firm surfaces.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  6. Q6.What type of hand signal means 'STOP' in crane operations?

    A.One arm raised horizontally
    B.Both hands flat, palms down, arms extended horizontally and moved back and forth
    C.Arm extended, palm down, holding position rigidly
    D.Both fists in front of body, thumbs pointing toward each other
    CArm extended, palm down, holding position rigidly

    Explanation: The STOP signal is given by extending the arm with palm down and holding the position rigidly. The EMERGENCY STOP signal uses both arms extended horizontally moving hands rapidly.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  7. Q7.A signal person must be provided when:

    A.The load is over 1,000 pounds
    B.The operator's view of the load or its path is obstructed
    C.The crane is being transported
    D.Only at night
    BThe operator's view of the load or its path is obstructed

    Explanation: A signal person is required when the point of operation is not in full view of the operator, when the operator's view is obstructed in the direction of travel, or when required by the site-specific safety plan.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  8. Q8.Wire rope must be removed from service when it has how many broken wires in one lay?

    A.2 broken wires
    B.4 broken wires
    C.6 broken wires in one rope lay or 3 broken wires in one strand in one rope lay
    D.10 broken wires
    C6 broken wires in one rope lay or 3 broken wires in one strand in one rope lay

    Explanation: Running wire rope must be taken out of service when it has 6 randomly distributed broken wires in one rope lay, or 3 broken wires in one strand in one rope lay.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  9. Q9.What must be done with the area beneath a suspended load?

    A.Work can continue normally
    B.Only the operator needs to be aware
    C.No employee should stand, walk, or work under a suspended load unless required by the work
    D.The area should be painted
    CNo employee should stand, walk, or work under a suspended load unless required by the work

    Explanation: No employee shall be permitted to stand, walk, or work under a suspended load, unless the employee is needed for the hooking or unhooking of the load.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  10. Q10.A qualified rigger is required for:

    A.Only lifts over 10 tons
    B.Assembly and disassembly of cranes
    C.All rigging operations where employees are involved in hooking, unhooking, guiding loads, or initial connection of a load to a component
    D.Only critical lifts
    CAll rigging operations where employees are involved in hooking, unhooking, guiding loads, or initial connection of a load to a component

    Explanation: A qualified rigger must be used for rigging operations, including hooking, unhooking, and guiding loads. The rigger must understand the principles of rigging and have the knowledge to ensure safety.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  11. Q11.Sling angles less than what degree from horizontal should not be used?

    A.15 degrees
    B.30 degrees
    C.45 degrees
    D.60 degrees
    B30 degrees

    Explanation: Sling angles of less than 30 degrees from horizontal should be avoided because the stress on each sling leg increases dramatically at lower angles, potentially exceeding the rated capacity.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  12. Q12.When must a crane's annual inspection be performed?

    A.Every 6 months
    B.At least once every 12 months
    C.Every 2 years
    D.Only when required by OSHA
    BAt least once every 12 months

    Explanation: A comprehensive inspection (annual inspection) must be performed at least every 12 months by a qualified person. Some components may require more frequent inspection.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  13. Q13.The weight of a rigging assembly (slings, shackles, hooks) must be subtracted from:

    A.The total cost of the lift
    B.The crane's rated capacity to determine the actual load that can be lifted
    C.The height of the lift
    D.Nothing; rigging weight is not considered
    BThe crane's rated capacity to determine the actual load that can be lifted

    Explanation: The weight of all rigging equipment (slings, shackles, blocks, etc.) is part of the total load and must be subtracted from the crane's rated capacity to determine the actual payload that can be lifted.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  14. Q14.Tag lines are used in crane operations to:

    A.Identify the load
    B.Control the load and prevent it from swinging or spinning
    C.Secure the crane to the ground
    D.Mark the lifting zone
    BControl the load and prevent it from swinging or spinning

    Explanation: Tag lines are ropes attached to the load to control its movement, prevent spinning, and guide the load into position. They are an important safety measure to prevent struck-by incidents.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  15. Q15.What is the minimum design factor for wire rope slings?

    A.3
    B.4
    C.5
    D.7
    C5

    Explanation: Wire rope slings must have a design factor of at least 5 (the breaking strength of the sling must be at least 5 times the rated capacity of the sling).

    Join 1,000+ users passing the OSHA 30-Hour Construction

  16. Q16.Before any crane lift, the operator must verify:

    A.Only the weather forecast
    B.That the load does not exceed the crane's rated capacity at the working radius
    C.Only the fuel level
    D.Only the operator's license
    BThat the load does not exceed the crane's rated capacity at the working radius

    Explanation: The operator must ensure that the load to be lifted does not exceed the rated capacity of the crane at the required radius and boom configuration. Overloading is a primary cause of crane accidents.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  17. Q17.Synthetic web slings must be removed from service when:

    A.They get dirty
    B.Acid or caustic burns, melting, charring, snags, punctures, or tears are present
    C.After 1 year of use regardless of condition
    D.They change color
    BAcid or caustic burns, melting, charring, snags, punctures, or tears are present

    Explanation: Synthetic web slings must be removed from service when they show acid or caustic burns, melting, charring, snags, punctures, tears, or other damage that compromises their integrity.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  18. Q18.A critical lift typically involves:

    A.Any lift under 1 ton
    B.A lift at or near the crane's maximum rated capacity, over occupied areas, or involving complex procedures
    C.Any routine lift
    D.Only lifts after 5 PM
    BA lift at or near the crane's maximum rated capacity, over occupied areas, or involving complex procedures

    Explanation: A critical lift is generally one that is at or near the maximum rated capacity of the crane (often defined as 75-90% of capacity), involves lifting over occupied areas, or requires complex rigging procedures.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  19. Q19.What is the purpose of a load moment indicator (LMI) on a crane?

    A.To measure wind speed
    B.To warn the operator when the load approaches the crane's rated capacity at the working radius
    C.To count the number of lifts
    D.To measure the height of the boom
    BTo warn the operator when the load approaches the crane's rated capacity at the working radius

    Explanation: A load moment indicator (LMI) monitors the load and radius and provides warnings to the operator as the load approaches the rated capacity, helping prevent overloading and tipping.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  20. Q20.When must rigging equipment be inspected?

    A.Monthly
    B.Before each use on each shift by a competent person
    C.Annually
    D.Only when damage is visible
    BBefore each use on each shift by a competent person

    Explanation: Rigging equipment for material handling shall be inspected before each use on each shift by a competent person and as necessary during its use to ensure that it is safe.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  21. Q21.Multi-leg slings carrying a load at a 60-degree angle from horizontal will have a capacity that is:

    A.The same as the full rated capacity
    B.Approximately 87% of the full rated capacity
    C.50% of the full rated capacity
    D.25% of the full rated capacity
    BApproximately 87% of the full rated capacity

    Explanation: The sling capacity decreases as the sling angle decreases from vertical. At 60 degrees from horizontal, each leg carries about 87% (sine of 60 degrees) of its rated capacity.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  22. Q22.What is the maximum wind speed at which most crane operations must cease?

    A.15 mph
    B.20 mph
    C.30 mph
    D.It depends on the manufacturer's specifications and the competent person's assessment
    DIt depends on the manufacturer's specifications and the competent person's assessment

    Explanation: There is no single OSHA-specified wind speed limit. Operations must cease when wind conditions create a hazardous situation, as determined by the competent person and the crane manufacturer's specifications.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  23. Q23.Employees being hoisted by a crane in a personnel platform must be protected by:

    A.Only a hard hat
    B.A personal fall arrest system attached to a structural member of the personnel platform
    C.Only guardrails on the platform
    D.No additional protection is needed
    BA personal fall arrest system attached to a structural member of the personnel platform

    Explanation: Employees being hoisted must use a personal fall arrest system with the lanyard attached to a structural member of the personnel platform. Guardrails are also required.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  24. Q24.The rated capacity of slings decreases when:

    A.The temperature increases
    B.The sling angle from horizontal decreases
    C.The sling is new
    D.The load is symmetrical
    BThe sling angle from horizontal decreases

    Explanation: As the sling angle from horizontal decreases, the load on each sling leg increases, effectively reducing the rated capacity of the sling assembly. This is why sling angles below 30 degrees should be avoided.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  25. Q25.A crane's operating radius is the distance from:

    A.The edge of the jobsite to the crane
    B.The center of rotation to the center of the load line
    C.The crane cab to the nearest building
    D.The ground to the top of the boom
    BThe center of rotation to the center of the load line

    Explanation: The operating radius is the horizontal distance from the axis of rotation (center pin) to the center of the vertical hoist line or load block. This distance determines the crane's rated capacity for that lift.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  26. Q26.The OSHA standard for cranes and derricks in construction is found in:

    A.29 CFR 1926 Subpart L
    B.29 CFR 1926 Subpart CC
    C.29 CFR 1926 Subpart M
    D.29 CFR 1926 Subpart H
    B29 CFR 1926 Subpart CC

    Explanation: Subpart CC of 29 CFR 1926 covers cranes and derricks in construction, including sections 1926.1400 through 1926.1442.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  27. Q27.When using shackles in rigging, the pin must be:

    A.Loosely fitted
    B.Properly seated and secured (never replace a bolt-type pin with a plain pin)
    C.Welded in place
    D.Painted a specific color
    BProperly seated and secured (never replace a bolt-type pin with a plain pin)

    Explanation: Shackle pins must be properly seated and secured. Using an improper pin or failing to secure the pin can result in the pin backing out and the load falling.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  28. Q28.Each sling must have a legible identification tag showing:

    A.The purchase date
    B.The manufacturer's name and rated capacity
    C.The project name
    D.The operator's name
    BThe manufacturer's name and rated capacity

    Explanation: Each sling shall be marked to show the rated capacities for the type of hitch used and the type of sling material. The manufacturer's name or trademark must also be visible.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  29. Q29.Personnel hoisting by crane is only permitted when:

    A.The crane operator agrees
    B.It is the least hazardous way to accomplish the task and conventional means of access are not feasible
    C.The weather is clear
    D.The lift is under 500 pounds
    BIt is the least hazardous way to accomplish the task and conventional means of access are not feasible

    Explanation: The use of a crane to hoist employees is permitted only when the erection, use, and dismantling of conventional means of reaching the work area would be more hazardous, or is not possible.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  30. Q30.An anti-two-block device on a crane prevents:

    A.Unauthorized crane use
    B.The load block from contacting the boom tip (two-blocking), which could cause failure
    C.The crane from tipping
    D.Power line contact
    BThe load block from contacting the boom tip (two-blocking), which could cause failure

    Explanation: An anti-two-block device warns the operator or automatically prevents the load block/ball from contacting the boom tip assembly, which could overload the wire rope and cause it to break.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  31. Q31.Alloy steel chain slings must be inspected for all of the following EXCEPT:

    A.Wear, nicks, and gouges
    B.Stretch beyond manufacturer limits
    C.Cracks and breaks
    D.Color changes
    DColor changes

    Explanation: Chain slings must be inspected for wear, nicks, cracks, breaks, gouges, stretch, and distortion. Color changes are not a standard inspection criterion for alloy steel chain slings.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  32. Q32.A crane assembly and disassembly must be directed by:

    A.Any employee
    B.A competent person or qualified person
    C.The crane manufacturer only
    D.OSHA
    BA competent person or qualified person

    Explanation: Assembly and disassembly must be directed by a qualified or competent person. The person directing must have adequate experience and training.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  33. Q33.When performing a multi-crane lift (two or more cranes lifting one load), a lift plan must:

    A.Not be required
    B.Be developed by a qualified person and reviewed by all involved operators
    C.Be verbal only
    D.Be created by the signal person
    BBe developed by a qualified person and reviewed by all involved operators

    Explanation: Multi-crane lifts require a detailed written lift plan developed by a qualified person. All operators must review and understand the plan before beginning the lift.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  34. Q34.The minimum design factor for alloy steel chain slings is:

    A.3
    B.4
    C.5
    D.7
    C5

    Explanation: Alloy steel chain slings shall have a minimum design factor of 5, meaning the breaking strength must be at least 5 times the rated capacity.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  35. Q35.What must happen before a crane is operated near power lines?

    A.Nothing special is required
    B.A hazard assessment must be conducted and precautions taken to maintain minimum clearance distances
    C.The power lines must always be de-energized
    D.Only the operator needs to be aware
    BA hazard assessment must be conducted and precautions taken to maintain minimum clearance distances

    Explanation: Before a crane is operated near power lines, a hazard assessment must identify all power lines within the work area, determine the voltages, and establish precautions to maintain safe clearance distances.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  36. Q36.The signal person must be:

    A.Any available employee
    B.Qualified by a third-party evaluator or employer's qualified evaluator
    C.The crane owner
    D.A licensed engineer
    BQualified by a third-party evaluator or employer's qualified evaluator

    Explanation: Signal persons must be qualified by either a third-party qualified evaluator or the employer's qualified evaluator. They must know and understand the standard hand signals and be competent in the application of required signals.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  37. Q37.A crane must not be operated unless it has which of the following safety devices in proper working order?

    A.Air horn
    B.Anti-two-block device, boom angle indicator, and load charts
    C.GPS tracking
    D.Backup camera
    BAnti-two-block device, boom angle indicator, and load charts

    Explanation: Cranes must have properly functioning safety devices including anti-two-block devices, boom angle or radius indicators, load charts, and other manufacturer-specified safety systems.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  38. Q38.What type of hitch provides the greatest sling capacity?

    A.Choker hitch
    B.Basket hitch
    C.Vertical hitch
    D.All hitches have equal capacity
    BBasket hitch

    Explanation: A basket hitch effectively doubles the capacity of a single vertical hitch because both legs of the sling bear the load. A choker hitch reduces capacity to approximately 75-80% of the rated vertical capacity.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  39. Q39.Crane operator certification is required for all operators of cranes with a capacity over:

    A.500 pounds
    B.1 ton (2,000 pounds)
    C.2,000 pounds
    D.All crane operators must be certified regardless of capacity
    B1 ton (2,000 pounds)

    Explanation: Operators of cranes with a rated capacity of more than 2,000 pounds must be certified by an accredited testing organization or qualified through the employer's program.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  40. Q40.When a load must travel over workers who cannot be moved, the lift director must:

    A.Allow it without restriction
    B.Ensure a critical lift plan is in place and all feasible protective measures are taken
    C.Cancel the lift
    D.Only notify the workers verbally
    BEnsure a critical lift plan is in place and all feasible protective measures are taken

    Explanation: Routes for suspended loads should be pre-planned to avoid passing over workers. When this is unavoidable, a detailed plan with protective measures must be implemented and all affected workers notified.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  41. Q41.What is the standard hand signal for 'Hoist' in crane operations?

    A.Arm extended horizontally with index finger pointing down, making circular motion
    B.Forearm vertical with index finger pointing up, making small horizontal circles
    C.Both arms extended palms down, moving arms back and forth
    D.One arm extended forward, thumb pointing up
    BForearm vertical with index finger pointing up, making small horizontal circles

    Explanation: The standard hand signal for 'Hoist' (raise the load) is the forearm held vertical with the index finger pointing up, making small horizontal circles. Standard hand signals are defined in OSHA's cranes and derricks standard.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  42. Q42.What is the standard hand signal for 'Emergency Stop' during crane operations?

    A.One arm extended with palm down
    B.Both arms extended palms down, swinging arms back and forth horizontally
    C.Clasp hands together in front of the body
    D.Arms crossed above the head
    BBoth arms extended palms down, swinging arms back and forth horizontally

    Explanation: The emergency stop signal is given by extending both arms horizontally to the sides with palms down and swinging the arms back and forth horizontally. This is distinct from the regular 'Stop' signal, which uses one arm extended with the palm down. All personnel on a crane operation site should know emergency stop signals.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  43. Q43.A load chart on a crane typically shows the relationship between:

    A.Wind speed and boom length
    B.Operating radius and the maximum rated capacity at that radius
    C.Crane age and maintenance schedule
    D.Ground conditions and outrigger extension
    BOperating radius and the maximum rated capacity at that radius

    Explanation: A crane's load chart shows the relationship between the operating radius (distance from the center of rotation to the center of the load) and the maximum rated capacity the crane can safely lift at that radius. As the radius increases, the rated capacity decreases. Operators must consult the load chart before every lift.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  44. Q44.When ground conditions are soft, what must be done before setting up a crane?

    A.Increase the load weight to test the ground
    B.Operate the crane at reduced capacity without further assessment
    C.The ground must be firm, drained, and graded to support the crane and load, using mats or cribbing as needed
    D.Only set up cranes on paved surfaces
    CThe ground must be firm, drained, and graded to support the crane and load, using mats or cribbing as needed

    Explanation: OSHA requires that the controlling entity must ensure the ground conditions are adequate to support the crane, the load, and any outriggers or other supporting structures. The ground must be firm, drained, and graded sufficiently. Timber mats, cribbing, or other means must be used to distribute loads when ground conditions are insufficient.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  45. Q45.An alloy steel shackle used in rigging should NEVER be:

    A.Used with wire rope slings
    B.Side-loaded beyond its design limits
    C.Stored indoors
    D.Painted with identification markings
    BSide-loaded beyond its design limits

    Explanation: Shackles should never be side-loaded beyond their design limits, as this can significantly reduce their rated capacity and lead to failure. Shackles are designed to carry loads in line with the pin. Side loading, point loading on the pin, or shock loading can cause the shackle to fail at loads well below its rated capacity.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  46. Q46.What is the purpose of a tag line in crane operations?

    A.To identify the crane owner
    B.To control the load and prevent uncontrolled swinging or spinning during a lift
    C.To measure the height of the boom
    D.To signal the crane operator
    BTo control the load and prevent uncontrolled swinging or spinning during a lift

    Explanation: Tag lines are ropes attached to the load that are held by workers on the ground to control the load's movement, preventing uncontrolled swinging, spinning, or rotation during the lift. They help guide the load to its intended landing spot safely and are especially important during windy conditions or when lifting loads with a large surface area.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  47. Q47.When must outriggers on a mobile crane be fully extended and set?

    A.Only for lifts exceeding 50% of rated capacity
    B.Only when the crane manufacturer recommends it
    C.Whenever the crane is performing a lift and the manufacturer's specifications require them
    D.Only during multi-crane lifts
    CWhenever the crane is performing a lift and the manufacturer's specifications require them

    Explanation: Outriggers must be fully extended and properly set whenever the crane manufacturer's specifications require them for the lift being performed. The load charts for most mobile cranes show different capacities depending on whether outriggers are extended or retracted. Operating without outriggers when they are required can lead to tipping.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  48. Q48.A crane operator must hold certification from an organization accredited by which body?

    A.OSHA directly
    B.A nationally accredited crane operator testing organization
    C.The crane manufacturer only
    D.The state department of labor only
    BA nationally accredited crane operator testing organization

    Explanation: Under OSHA's crane standard, crane operators must be certified by an accredited crane operator testing organization. The accreditation must be by a nationally recognized accrediting agency. Certification must be for the specific type of crane the operator will be using. Examples of accredited organizations include NCCCO, CIC, and NCCER.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  49. Q49.When using a wire rope sling, which of the following conditions requires the sling to be immediately removed from service?

    A.Slight discoloration from normal use
    B.Minor fraying that does not exceed manufacturer specifications
    C.Kinking, crushing, bird-caging, or any distortion of the rope structure
    D.Surface rust that can be wiped off
    CKinking, crushing, bird-caging, or any distortion of the rope structure

    Explanation: Wire rope slings must be immediately removed from service when there is evidence of kinking, crushing, bird-caging, or any other distortion of the rope structure. These conditions indicate significant internal damage that compromises the sling's load-bearing capacity and integrity. Other removal criteria include broken wires exceeding limits, corrosion, heat damage, and end attachment wear.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  50. Q50.When working near power lines rated over 50kV, the minimum clearance distance for a crane's boom increases by how much for each additional 10kV?

    A.2 inches per 10kV
    B.4 inches (0.4 meters) per 10kV over 50kV
    C.1 foot per 10kV
    D.6 inches per 10kV
    B4 inches (0.4 meters) per 10kV over 50kV

    Explanation: For power lines over 50kV, the minimum clearance distance of 10 feet must be increased by 4 inches (0.4 meters) for each additional 10kV over 50kV. For example, a 200kV line would require a clearance of 10 feet plus 15 x 4 inches = 60 inches (5 feet), totaling 15 feet of clearance. This protects against electrical arcing.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  51. Q51.Which type of synthetic sling must be protected from sharp edges, abrasion, and cutting during use?

    A.Alloy steel chain slings only
    B.All synthetic web and round slings
    C.Only polyester slings
    D.Wire rope slings only
    BAll synthetic web and round slings

    Explanation: All synthetic web slings and synthetic round slings must be protected from sharp edges, abrasion, and cutting. Padding or corner protectors should be used when the sling contacts sharp edges of a load. Contact with sharp surfaces can sever or weaken synthetic fibers, leading to sling failure. Synthetic slings must also be protected from heat, chemicals, and UV degradation.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  52. Q52.During crane assembly or disassembly, what is the role of the A/D (Assembly/Disassembly) director?

    A.To operate the crane during assembly
    B.To ensure the A/D process is performed in accordance with manufacturer procedures and site-specific conditions, and to direct the work
    C.To inspect the crane after assembly only
    D.To order replacement parts for the crane
    BTo ensure the A/D process is performed in accordance with manufacturer procedures and site-specific conditions, and to direct the work

    Explanation: The A/D director must be a competent person or a qualified person who must direct the assembly and disassembly process. Their responsibilities include ensuring the process follows manufacturer procedures, managing site-specific conditions, and overseeing the crew to ensure safety. The A/D director must understand and apply all applicable procedures.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  53. Q53.A lift plan for a critical lift must include all of the following EXCEPT:

    A.The weight of the load and rigging
    B.The resumes of all workers on site
    C.The crane's rated capacity at the planned radius
    D.Identification of hazards and the steps to address them
    BThe resumes of all workers on site

    Explanation: A critical lift plan must include the weight of the load, rigging weight, the crane's rated capacity at the planned radius, environmental conditions, ground conditions, hazard identification and mitigation steps, communication procedures, and a detailed sequence of operations. Resumes of workers are not a required component of a lift plan.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  54. Q54.What is the minimum clearance distance between a crane boom and a power line of 50kV or less?

    A.5 feet
    B.10 feet
    C.15 feet
    D.20 feet
    B10 feet

    Explanation: The minimum clearance distance between any part of the crane, load line, or load and a power line rated 50kV or less is 10 feet. This clearance must be maintained at all times during crane operation. Special precautions, including designated observers and range-limiting devices, may be required when working near power lines.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  55. Q55.A load moment indicator (LMI) monitors which critical parameters during a crane lift?

    A.Wind speed and temperature only
    B.Boom length, boom angle, and load weight to calculate the load moment and warn of overloading
    C.The operator's heart rate and alertness
    D.Fuel level and engine RPM
    BBoom length, boom angle, and load weight to calculate the load moment and warn of overloading

    Explanation: A load moment indicator (LMI) is a device that continuously monitors the boom length, boom angle, and the weight of the load to calculate the load moment (the product of the load weight and the radius). It warns the operator when the load approaches or exceeds the crane's rated capacity at the given radius, helping prevent tipping and structural failure.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  56. Q56.What documentation must a crane operator possess while operating a crane on a construction site?

    A.Only a valid driver's license
    B.A valid crane operator certification for the type of crane being operated and documentation of medical fitness
    C.A college degree in mechanical engineering
    D.A general construction safety card only
    BA valid crane operator certification for the type of crane being operated and documentation of medical fitness

    Explanation: Crane operators must possess and have readily available valid certification from an accredited testing organization for the specific type of crane being operated. They must also meet the medical fitness requirements. The employer must ensure that operators are competent to safely operate the specific type and configuration of crane they are using.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  57. Q57.In a multi-crane lift involving two cranes lifting a single load, what is the MOST critical planning requirement?

    A.Both cranes must be the same make and model
    B.A detailed lift plan must be developed that accounts for load sharing, communication, sequence of operations, and potential hazards
    C.Only one signal person is needed for both cranes
    D.Multi-crane lifts do not require any special planning beyond a normal lift
    BA detailed lift plan must be developed that accounts for load sharing, communication, sequence of operations, and potential hazards

    Explanation: Multi-crane lifts are among the most hazardous crane operations. A detailed lift plan must be developed by a qualified person, accounting for the load distribution between cranes, precise communication procedures between all parties, the sequence of operations for lifting and lowering, and all potential hazards. Each crane must be operated within its rated capacity during all phases of the lift.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  58. Q58.A wire rope on a running rope (such as a hoist line) must be taken out of service when the number of broken wires in one rope lay exceeds:

    A.3 broken wires
    B.6 broken wires in one lay or 3 in one strand
    C.12 broken wires
    D.Any single broken wire requires immediate replacement
    B6 broken wires in one lay or 3 in one strand

    Explanation: For running ropes (such as hoist lines), the wire rope must be removed from service when there are 6 randomly distributed broken wires in one rope lay, or 3 broken wires in one strand in one rope lay. Additional removal criteria include evidence of heat damage, kinking, crushing, bird-caging, corrosion, broken or missing wires at fittings, and reduction of rope diameter beyond allowable limits.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  59. Q59.When calculating the effective capacity of a sling in a choker hitch configuration, the rated capacity is reduced to approximately what percentage of the straight (vertical) hitch capacity?

    A.100% (no reduction)
    B.75%
    C.50%
    D.25%
    B75%

    Explanation: A choker hitch reduces the effective capacity of a sling to approximately 75% of its vertical hitch rated capacity. This reduction occurs because the choker configuration creates a bending stress at the choke point. The actual capacity also depends on the angle of choke; a choke angle less than 120 degrees can further reduce the capacity. Riggers must always account for this reduction when selecting slings.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  60. Q60.During the monthly wire rope inspection of a crane, the inspector finds a section of wire rope that has a diameter reduction of 6% from the nominal diameter. What action is required?

    A.No action needed; this is within normal wear limits
    B.Increase the frequency of inspections but continue to use the rope
    C.The rope must be removed from service, as any diameter reduction exceeding 5% requires removal for running ropes
    D.Apply lubricant and recheck in one week
    CThe rope must be removed from service, as any diameter reduction exceeding 5% requires removal for running ropes

    Explanation: A wire rope must be removed from service when the actual diameter is reduced by more than 5% from the nominal diameter for running ropes (such as hoist lines). This diameter reduction indicates significant internal and external wear or core deterioration that compromises the rope's breaking strength. The monthly inspection must include checking the rope diameter and comparing it to the nominal diameter.

    Join 1,000+ users passing the OSHA 30-Hour Construction

Want all 700 questions?

Download VoltExam — $17.99 Lifetime

Offline access, 700+ questions, built-in calculators. One-time unlock, no subscription.

Download on the App Store

More OSHA 30-Hour Construction Exam Topics