Skip to main content

OSHA 30-Hour Construction Exam

Steel Erection Practice Questions

20 practice questions with detailed explanations — aligned to the OSHA 30-Hour Construction Exam.

  1. Q1.Under the steel erection standard, what is the minimum number of anchor bolts required per column?

    A.2
    B.4
    C.6
    D.8
    B4

    Explanation: OSHA requires a minimum of four anchor bolts per column to ensure structural stability during steel erection. All anchor bolts must be set in accordance with approved erection drawings and the bolts must be tight enough to support the column loads during erection.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  2. Q2.At what height does OSHA require fall protection for workers engaged in steel erection activities?

    A.6 feet
    B.10 feet
    C.15 feet
    D.25 feet
    C15 feet

    Explanation: In steel erection, fall protection is generally required for workers at heights of 15 feet or more above a lower level, rather than the standard 6-foot trigger height used in general construction. This is a specific exception under Subpart R.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  3. Q3.What is a controlled decking zone (CDZ) in steel erection?

    A.A zone where all workers must use guardrails
    B.A designated area where metal decking may be installed without the use of conventional fall protection, under specified conditions
    C.A zone where cranes are not permitted
    D.An area designated for material storage only
    BA designated area where metal decking may be installed without the use of conventional fall protection, under specified conditions

    Explanation: A controlled decking zone (CDZ) is a defined area of the structure where initial installation and placement of metal deck occurs without conventional fall protection. The CDZ has strict size limitations and operational requirements to protect workers.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  4. Q4.What is a 'connector' in steel erection?

    A.A type of bolt used to join steel members
    B.An employee who works at heights connecting structural steel members while they are being hoisted
    C.A safety device attached to a harness
    D.A type of welding technique
    BAn employee who works at heights connecting structural steel members while they are being hoisted

    Explanation: A connector is an employee who, working with hoisting equipment, is placing and connecting structural members and/or components. Connectors have special fall protection provisions due to the nature of their work, which requires mobility and the ability to reach connection points.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  5. Q5.What is the fall protection trigger height for connectors working between two columns during steel erection?

    A.6 feet
    B.10 feet
    C.15 feet
    D.30 feet
    C15 feet

    Explanation: Connectors must be protected from fall hazards at heights greater than two stories or 30 feet, whichever is less. However, at heights between 15 and 30 feet, connectors must have a personal fall arrest system or be able to be tied off, or wear the equipment necessary to be tied off, and be able to demonstrate that tying off is infeasible.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  6. Q6.What is the purpose of a perimeter safety cable in steel erection?

    A.To carry electrical power to welding equipment
    B.To serve as a fall protection barrier around the perimeter of the structure being erected
    C.To guide the crane during hoisting
    D.To secure the building to the foundation
    BTo serve as a fall protection barrier around the perimeter of the structure being erected

    Explanation: Perimeter safety cables are installed around the perimeter of the structure being erected to serve as a fall protection barrier for workers. They must be installed at the final interior and exterior perimeters of multi-story structures as soon as the decking has been installed.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  7. Q7.What is a 'double connection' in steel erection?

    A.Using two cranes to lift a single beam
    B.An attachment to a supporting member where the weights of two structural members are supported on a single connection point
    C.Connecting two safety lanyards to one anchor point
    D.Using two bolts where one is specified
    BAn attachment to a supporting member where the weights of two structural members are supported on a single connection point

    Explanation: A double connection is where the weights of two structural members are supported on a single connection point. Double connections are not permitted for structural steel members unless the first member is stabilized through adequate connection of additional structural members before the second piece is placed.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  8. Q8.Steel erection workers must receive training on all of the following EXCEPT:

    A.Fall hazard awareness
    B.Multiple-lift rigging procedures
    C.Connector procedures
    D.Project cost estimation
    DProject cost estimation

    Explanation: Steel erection workers must receive training in fall hazard awareness, multiple-lift rigging (if applicable), connector procedures, controlled decking zone procedures, and other hazards associated with steel erection. Project cost estimation is not a safety training requirement.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  9. Q9.Before steel erection begins, the controlling contractor must provide the steel erector with a written notification certifying that which of the following is complete?

    A.All plumbing and electrical rough-ins
    B.Concrete in footings, piers, and walls has adequately cured to support steel loads
    C.Landscaping around the building perimeter
    D.Roofing materials have been delivered
    BConcrete in footings, piers, and walls has adequately cured to support steel loads

    Explanation: The controlling contractor must provide written notification to the steel erector certifying that concrete in footings, piers, and walls, as well as other support systems, has attained sufficient strength to support the loads imposed during steel erection.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  10. Q10.During multi-story steel erection, how many bolts must be installed in a connection before the hoisting equipment is released?

    A.All bolts specified in the design
    B.At least two bolts per connection, drawn up wrench-tight
    C.One bolt per connection
    D.No bolts are required until the structure is fully erected
    BAt least two bolts per connection, drawn up wrench-tight

    Explanation: At least two bolts per connection must be installed and drawn up wrench-tight before the hoisting equipment can be released from the member. This is a minimum requirement to ensure the structural integrity of the connection before the load is transferred.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  11. Q11.What is plumbing-up in the context of steel erection?

    A.Installing water supply pipes in a building
    B.The process of aligning and leveling the structural steel frame to ensure it is plumb and true
    C.Installing drains on the roof
    D.Testing fire sprinkler systems
    BThe process of aligning and leveling the structural steel frame to ensure it is plumb and true

    Explanation: Plumbing-up is the process of adjusting the structural steel framework to ensure it is vertically plumb (straight up and down) and the connections are properly aligned. Guy cables, turnbuckles, and temporary bracing are used during this process, and no loading is placed on the structure until plumbing-up is complete.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  12. Q12.Shear connectors (studs and similar devices) must not be attached to the top flange of a beam until which condition is met?

    A.The beam has been painted
    B.The metal decking or other walking/working surface has been installed
    C.The beam has been inspected by a third party
    D.All bolts in the connection have been fully torqued
    BThe metal decking or other walking/working surface has been installed

    Explanation: Shear connectors (headed studs, etc.) must not be attached to the top flanges of beams, joists, or beam attachments until the metal decking or other walking/working surface has been installed. This is to prevent creating a tripping hazard on walking surfaces.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  13. Q13.What is the maximum width of a controlled decking zone (CDZ)?

    A.45 feet
    B.60 feet
    C.90 feet
    D.120 feet
    C90 feet

    Explanation: A controlled decking zone (CDZ) must not exceed 90 feet wide and must not exceed the width of the building. The CDZ is the defined area where initial placement of metal deck occurs without conventional fall protection, subject to strict operational controls.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  14. Q14.During steel erection, falling object protection must include all of the following EXCEPT:

    A.Securing loose items and materials against falling
    B.Not placing materials on structures being erected unless they are secured
    C.Barricading areas below overhead work
    D.Requiring all ground workers to wear steel-toed sandals
    DRequiring all ground workers to wear steel-toed sandals

    Explanation: Falling object protection during steel erection includes securing tools and materials against displacement, not placing items on steel being erected unless secured, barricading areas below, and wearing hard hats. Steel-toed sandals are not acceptable protective footwear on any construction site.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  15. Q15.Column splices in steel erection must be designed to resist which of the following?

    A.Only vertical compression loads
    B.A minimum eccentric gravity load of 300 pounds located 18 inches from the column face in each direction
    C.Wind loads only
    D.Lateral loads only
    BA minimum eccentric gravity load of 300 pounds located 18 inches from the column face in each direction

    Explanation: Each column splice must be designed to resist a minimum eccentric gravity load of 300 pounds located 18 inches from the extreme outer face of the column in each direction at the top of the column shaft. This ensures stability during the erection process before final connections are completed.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  16. Q16.Walking/working surfaces in steel erection must meet which minimum requirement for metal decking?

    A.Decking must be painted with a non-slip coating
    B.Metal decking bundles must be placed on the steel structure only in designated areas and secured against displacement
    C.All decking must be installed within 24 hours of steel placement
    D.Decking is not required until the building is enclosed
    BMetal decking bundles must be placed on the steel structure only in designated areas and secured against displacement

    Explanation: Metal decking bundles must be landed on the structure only in designated areas and must be secured to prevent displacement or sliding. Unsecured decking bundles can become unstable and fall from the structure, creating serious hazards to workers below.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  17. Q17.In a multiple-lift rigging procedure during steel erection, what is the maximum number of members that may be hoisted in a single lift?

    A.3 members
    B.5 members
    C.7 members
    D.No specific limit if engineered properly
    B5 members

    Explanation: In a multiple-lift rigging procedure, no more than five members may be hoisted per lift. The rigging must be designed by a qualified rigger, the members must be rigged from top down with the heaviest member on the bottom, and tag lines must be used to control the load.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  18. Q18.A steel erection site-specific erection plan is required when which of the following conditions exists?

    A.For every steel erection project regardless of size
    B.When a structure is more than one story
    C.When the structure or portion of the structure has been predesigned for erection using a multiple-lift rigging procedure, or when there are unusual site conditions
    D.Only when required by the building owner
    CWhen the structure or portion of the structure has been predesigned for erection using a multiple-lift rigging procedure, or when there are unusual site conditions

    Explanation: A site-specific erection plan is required when the erection involves multiple-lift rigging procedures or other conditions that the standard identifies as requiring specific planning. The plan must be developed by a qualified person and made available at the site.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  19. Q19.During steel erection, hoisting equipment must not be used to hoist personnel except when which conditions are met?

    A.When the crane is rated for personnel hoisting
    B.When there is no other practical means of access and the equipment meets specific OSHA requirements for personnel hoisting
    C.When the operator has more than 5 years of experience
    D.Personnel hoisting during steel erection is always prohibited
    BWhen there is no other practical means of access and the equipment meets specific OSHA requirements for personnel hoisting

    Explanation: Hoisting employees on a personnel platform is allowed only when there is no other safe means of access. The crane must meet specific OSHA requirements including a trial lift, anti-two-block device, and the load must not exceed 50% of the rated capacity for the crane's configuration.

    Join 1,000+ users passing the OSHA 30-Hour Construction

  20. Q20.Open web steel joists during erection must not be placed on a support structure unless the structure can support the weight of at least how many joists without exceeding its design capacity?

    A.The weight of one joist
    B.The weight of all joists in the immediate bay
    C.At a minimum, the weight of the joists within the erection span plus the weight of the bundle of joists being placed, without exceeding the capacity
    D.The total weight of the entire structure
    CAt a minimum, the weight of the joists within the erection span plus the weight of the bundle of joists being placed, without exceeding the capacity

    Explanation: Before placing open web steel joists, the bearing seat or support structure must be verified to support the cumulative weight of the joists placed within the span, plus any bundle of joists being placed, without exceeding its design capacity. Overloading during erection can cause structural failure and collapse.

    Join 1,000+ users passing the OSHA 30-Hour Construction

Want all 700 questions?

Download VoltExam — $17.99 Lifetime

Offline access, 700+ questions, built-in calculators. One-time unlock, no subscription.

Download on the App Store

More OSHA 30-Hour Construction Exam Topics