OSHA 30-Hour Construction Exam
Steel Erection Practice Questions
20 practice questions with detailed explanations — aligned to the OSHA 30-Hour Construction Exam.
Q1.Under the steel erection standard, what is the minimum number of anchor bolts required per column?
A.2B.4C.6D.8B. 4Explanation: OSHA requires a minimum of four anchor bolts per column to ensure structural stability during steel erection. All anchor bolts must be set in accordance with approved erection drawings and the bolts must be tight enough to support the column loads during erection.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q2.At what height does OSHA require fall protection for workers engaged in steel erection activities?
A.6 feetB.10 feetC.15 feetD.25 feetC. 15 feetExplanation: In steel erection, fall protection is generally required for workers at heights of 15 feet or more above a lower level, rather than the standard 6-foot trigger height used in general construction. This is a specific exception under Subpart R.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q3.What is a controlled decking zone (CDZ) in steel erection?
A.A zone where all workers must use guardrailsB.A designated area where metal decking may be installed without the use of conventional fall protection, under specified conditionsC.A zone where cranes are not permittedD.An area designated for material storage onlyB. A designated area where metal decking may be installed without the use of conventional fall protection, under specified conditionsExplanation: A controlled decking zone (CDZ) is a defined area of the structure where initial installation and placement of metal deck occurs without conventional fall protection. The CDZ has strict size limitations and operational requirements to protect workers.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q4.What is a 'connector' in steel erection?
A.A type of bolt used to join steel membersB.An employee who works at heights connecting structural steel members while they are being hoistedC.A safety device attached to a harnessD.A type of welding techniqueB. An employee who works at heights connecting structural steel members while they are being hoistedExplanation: A connector is an employee who, working with hoisting equipment, is placing and connecting structural members and/or components. Connectors have special fall protection provisions due to the nature of their work, which requires mobility and the ability to reach connection points.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q5.What is the fall protection trigger height for connectors working between two columns during steel erection?
A.6 feetB.10 feetC.15 feetD.30 feetC. 15 feetExplanation: Connectors must be protected from fall hazards at heights greater than two stories or 30 feet, whichever is less. However, at heights between 15 and 30 feet, connectors must have a personal fall arrest system or be able to be tied off, or wear the equipment necessary to be tied off, and be able to demonstrate that tying off is infeasible.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q6.What is the purpose of a perimeter safety cable in steel erection?
A.To carry electrical power to welding equipmentB.To serve as a fall protection barrier around the perimeter of the structure being erectedC.To guide the crane during hoistingD.To secure the building to the foundationB. To serve as a fall protection barrier around the perimeter of the structure being erectedExplanation: Perimeter safety cables are installed around the perimeter of the structure being erected to serve as a fall protection barrier for workers. They must be installed at the final interior and exterior perimeters of multi-story structures as soon as the decking has been installed.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q7.What is a 'double connection' in steel erection?
A.Using two cranes to lift a single beamB.An attachment to a supporting member where the weights of two structural members are supported on a single connection pointC.Connecting two safety lanyards to one anchor pointD.Using two bolts where one is specifiedB. An attachment to a supporting member where the weights of two structural members are supported on a single connection pointExplanation: A double connection is where the weights of two structural members are supported on a single connection point. Double connections are not permitted for structural steel members unless the first member is stabilized through adequate connection of additional structural members before the second piece is placed.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q8.Steel erection workers must receive training on all of the following EXCEPT:
A.Fall hazard awarenessB.Multiple-lift rigging proceduresC.Connector proceduresD.Project cost estimationD. Project cost estimationExplanation: Steel erection workers must receive training in fall hazard awareness, multiple-lift rigging (if applicable), connector procedures, controlled decking zone procedures, and other hazards associated with steel erection. Project cost estimation is not a safety training requirement.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q9.Before steel erection begins, the controlling contractor must provide the steel erector with a written notification certifying that which of the following is complete?
A.All plumbing and electrical rough-insB.Concrete in footings, piers, and walls has adequately cured to support steel loadsC.Landscaping around the building perimeterD.Roofing materials have been deliveredB. Concrete in footings, piers, and walls has adequately cured to support steel loadsExplanation: The controlling contractor must provide written notification to the steel erector certifying that concrete in footings, piers, and walls, as well as other support systems, has attained sufficient strength to support the loads imposed during steel erection.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q10.During multi-story steel erection, how many bolts must be installed in a connection before the hoisting equipment is released?
A.All bolts specified in the designB.At least two bolts per connection, drawn up wrench-tightC.One bolt per connectionD.No bolts are required until the structure is fully erectedB. At least two bolts per connection, drawn up wrench-tightExplanation: At least two bolts per connection must be installed and drawn up wrench-tight before the hoisting equipment can be released from the member. This is a minimum requirement to ensure the structural integrity of the connection before the load is transferred.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q11.What is plumbing-up in the context of steel erection?
A.Installing water supply pipes in a buildingB.The process of aligning and leveling the structural steel frame to ensure it is plumb and trueC.Installing drains on the roofD.Testing fire sprinkler systemsB. The process of aligning and leveling the structural steel frame to ensure it is plumb and trueExplanation: Plumbing-up is the process of adjusting the structural steel framework to ensure it is vertically plumb (straight up and down) and the connections are properly aligned. Guy cables, turnbuckles, and temporary bracing are used during this process, and no loading is placed on the structure until plumbing-up is complete.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q12.Shear connectors (studs and similar devices) must not be attached to the top flange of a beam until which condition is met?
A.The beam has been paintedB.The metal decking or other walking/working surface has been installedC.The beam has been inspected by a third partyD.All bolts in the connection have been fully torquedB. The metal decking or other walking/working surface has been installedExplanation: Shear connectors (headed studs, etc.) must not be attached to the top flanges of beams, joists, or beam attachments until the metal decking or other walking/working surface has been installed. This is to prevent creating a tripping hazard on walking surfaces.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q13.What is the maximum width of a controlled decking zone (CDZ)?
A.45 feetB.60 feetC.90 feetD.120 feetC. 90 feetExplanation: A controlled decking zone (CDZ) must not exceed 90 feet wide and must not exceed the width of the building. The CDZ is the defined area where initial placement of metal deck occurs without conventional fall protection, subject to strict operational controls.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q14.During steel erection, falling object protection must include all of the following EXCEPT:
A.Securing loose items and materials against fallingB.Not placing materials on structures being erected unless they are securedC.Barricading areas below overhead workD.Requiring all ground workers to wear steel-toed sandalsD. Requiring all ground workers to wear steel-toed sandalsExplanation: Falling object protection during steel erection includes securing tools and materials against displacement, not placing items on steel being erected unless secured, barricading areas below, and wearing hard hats. Steel-toed sandals are not acceptable protective footwear on any construction site.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q15.Column splices in steel erection must be designed to resist which of the following?
A.Only vertical compression loadsB.A minimum eccentric gravity load of 300 pounds located 18 inches from the column face in each directionC.Wind loads onlyD.Lateral loads onlyB. A minimum eccentric gravity load of 300 pounds located 18 inches from the column face in each directionExplanation: Each column splice must be designed to resist a minimum eccentric gravity load of 300 pounds located 18 inches from the extreme outer face of the column in each direction at the top of the column shaft. This ensures stability during the erection process before final connections are completed.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q16.Walking/working surfaces in steel erection must meet which minimum requirement for metal decking?
A.Decking must be painted with a non-slip coatingB.Metal decking bundles must be placed on the steel structure only in designated areas and secured against displacementC.All decking must be installed within 24 hours of steel placementD.Decking is not required until the building is enclosedB. Metal decking bundles must be placed on the steel structure only in designated areas and secured against displacementExplanation: Metal decking bundles must be landed on the structure only in designated areas and must be secured to prevent displacement or sliding. Unsecured decking bundles can become unstable and fall from the structure, creating serious hazards to workers below.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q17.In a multiple-lift rigging procedure during steel erection, what is the maximum number of members that may be hoisted in a single lift?
A.3 membersB.5 membersC.7 membersD.No specific limit if engineered properlyB. 5 membersExplanation: In a multiple-lift rigging procedure, no more than five members may be hoisted per lift. The rigging must be designed by a qualified rigger, the members must be rigged from top down with the heaviest member on the bottom, and tag lines must be used to control the load.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q18.A steel erection site-specific erection plan is required when which of the following conditions exists?
A.For every steel erection project regardless of sizeB.When a structure is more than one storyC.When the structure or portion of the structure has been predesigned for erection using a multiple-lift rigging procedure, or when there are unusual site conditionsD.Only when required by the building ownerC. When the structure or portion of the structure has been predesigned for erection using a multiple-lift rigging procedure, or when there are unusual site conditionsExplanation: A site-specific erection plan is required when the erection involves multiple-lift rigging procedures or other conditions that the standard identifies as requiring specific planning. The plan must be developed by a qualified person and made available at the site.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q19.During steel erection, hoisting equipment must not be used to hoist personnel except when which conditions are met?
A.When the crane is rated for personnel hoistingB.When there is no other practical means of access and the equipment meets specific OSHA requirements for personnel hoistingC.When the operator has more than 5 years of experienceD.Personnel hoisting during steel erection is always prohibitedB. When there is no other practical means of access and the equipment meets specific OSHA requirements for personnel hoistingExplanation: Hoisting employees on a personnel platform is allowed only when there is no other safe means of access. The crane must meet specific OSHA requirements including a trial lift, anti-two-block device, and the load must not exceed 50% of the rated capacity for the crane's configuration.
Join 1,000+ users passing the OSHA 30-Hour Construction
Q20.Open web steel joists during erection must not be placed on a support structure unless the structure can support the weight of at least how many joists without exceeding its design capacity?
A.The weight of one joistB.The weight of all joists in the immediate bayC.At a minimum, the weight of the joists within the erection span plus the weight of the bundle of joists being placed, without exceeding the capacityD.The total weight of the entire structureC. At a minimum, the weight of the joists within the erection span plus the weight of the bundle of joists being placed, without exceeding the capacityExplanation: Before placing open web steel joists, the bearing seat or support structure must be verified to support the cumulative weight of the joists placed within the span, plus any bundle of joists being placed, without exceeding its design capacity. Overloading during erection can cause structural failure and collapse.
Join 1,000+ users passing the OSHA 30-Hour Construction
Want all 700 questions?
Download VoltExam — $17.99 Lifetime
Offline access, 700+ questions, built-in calculators. One-time unlock, no subscription.
Download on the App Store