Skip to main content

Lean Six Sigma Exam

Process Capability (Cp, Cpk, Sigma Level) Practice Questions

10 practice questions with detailed explanations — aligned to the Lean Six Sigma Exam.

Master Process Capability (Cp, Cpk, Sigma Level) to boost your score on the Lean Six Sigma Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 10 questions, review any that trip you up, and use the related topics below to round out your preparation.

  1. Q1.What is the difference between Cp and Cpk?

    A.Cp measures long-term capability; Cpk measures short-term capability
    B.Cp measures potential capability (centered); Cpk accounts for process centering
    C.Cp is for two-sided specs; Cpk is for one-sided specs
    D.Cp uses the mean; Cpk uses the median
    BCp measures potential capability (centered); Cpk accounts for process centering

    Explanation: Cp (process capability ratio) measures potential capability assuming the process is perfectly centered between the specification limits. Cpk is the actual capability index — it accounts for where the process mean sits relative to both limits. A process can have high Cp (wide spec relative to variation) but low Cpk if the mean is off-center.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  2. Q2.A process has Cpk = 1.00. What is the approximate DPMO (defects per million opportunities)?

    A.66,807
    B.3,400
    C.233
    D.2,700
    D2,700

    Explanation: A Cpk of 1.00 corresponds to ±3 sigma performance, which yields approximately 2,700 DPMO (2,700 defects per million opportunities) — assuming a centered normal distribution. This equates to roughly 99.73% yield. A Cpk of 1.33 corresponds to ±4 sigma (~63 DPMO) and a Cpk of 1.67 to ±5 sigma (~0.57 DPMO).

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  3. Q3.What sigma level corresponds to 3.4 DPMO, the Six Sigma standard?

    A.4 sigma
    B.5 sigma
    C.6 sigma
    D.5.5 sigma
    C6 sigma

    Explanation: Six Sigma quality = 3.4 DPMO. This is achieved at ±6 sigma with a 1.5-sigma long-term shift allowance (the standard Motorola convention). Without the shift, ±6 sigma would yield ~0.002 DPMO. The 3.4 DPMO target accounts for typical long-term process drift.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  4. Q4.A process has USL = 20, LSL = 10, mean = 14, and standard deviation = 1. What is the Cpk?

    A.1.00
    B.1.33
    C.1.67
    D.0.83
    B1.33

    Explanation: Cpk = min[(USL − mean)/(3σ), (mean − LSL)/(3σ)] = min[(20−14)/(3×1), (14−10)/(3×1)] = min[6/3, 4/3] = min[2.00, 1.33] = 1.33. The lower tail is the binding constraint because the mean is shifted toward the LSL.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  5. Q5.When a process is 'capable' but 'not stable,' what is the recommended action?

    A.Proceed — capability is all that matters
    B.Investigate and eliminate assignable causes before assessing capability
    C.Widen the specification limits
    D.Increase sample size and recalculate Cpk
    BInvestigate and eliminate assignable causes before assessing capability

    Explanation: Process capability indices (Cp, Cpk) are only meaningful when the process is in statistical control (stable). If a control chart shows out-of-control signals (special causes), Cpk calculations are unreliable. You must first identify and eliminate assignable causes, bringing the process into control, before evaluating capability.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  6. Q6.A process has a Cpk of 0.8. What does this indicate?

    A.The process is not capable — defects are occurring outside specification limits
    B.The process is exactly meeting specifications with no margin
    C.The process is highly capable with Six Sigma quality
    D.The process mean is perfectly centered between spec limits
    AThe process is not capable — defects are occurring outside specification limits

    Explanation: Cpk measures how centered and capable a process is relative to specification limits. A Cpk below 1.0 means the process is producing output outside one or both spec limits — it is not capable. A Cpk ≥ 1.33 is typically considered capable.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  7. Q7.What is the difference between Cp and Cpk?

    A.Cp measures potential capability assuming a centered process; Cpk accounts for how centered the mean actually is
    B.Cp measures short-term capability; Cpk measures long-term capability
    C.Cp uses sample data; Cpk uses population data
    D.Cp is for one-sided specs; Cpk is for two-sided specs
    ACp measures potential capability assuming a centered process; Cpk accounts for how centered the mean actually is

    Explanation: Cp = (USL – LSL) / (6σ) and measures the spread of the process relative to specification width — assuming the mean is perfectly centered. Cpk adjusts for process mean shift by taking the minimum of (USL – mean)/3σ and (mean – LSL)/3σ.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  8. Q8.A process must achieve a Cpk ≥ 1.67 to meet customer requirements. What sigma level does this approximately correspond to?

    A.5 sigma
    B.3 sigma
    C.6 sigma
    D.4 sigma
    A5 sigma

    Explanation: Cpk of 1.67 corresponds to a 5-sigma process. The relationship is: sigma level ≈ 3 × Cpk. So Cpk 1.00 ≈ 3σ, Cpk 1.33 ≈ 4σ, Cpk 1.67 ≈ 5σ, and Cpk 2.00 ≈ 6σ.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  9. Q9.Which of the following is a prerequisite for a meaningful process capability study?

    A.The process must be in statistical control (stable)
    B.The process must be running above 100 units per hour
    C.The Cpk must already exceed 1.0
    D.The data must follow a uniform distribution
    AThe process must be in statistical control (stable)

    Explanation: Capability indices (Cp, Cpk) are only meaningful when the process is stable — i.e., in statistical control with no special causes. Calculating Cpk on an unstable process produces misleading results because the variation is not predictable.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  10. Q10.Long-term process capability is measured by Ppk, while short-term is measured by Cpk. What is the typical relationship between these two indices?

    A.Ppk ≤ Cpk because long-term data includes more sources of variation
    B.Ppk > Cpk because more data provides a better estimate
    C.Ppk = Cpk when the process is normally distributed
    D.Ppk and Cpk are calculated identically from the same data
    APpk ≤ Cpk because long-term data includes more sources of variation

    Explanation: Ppk uses the overall (long-term) standard deviation from all data collected, while Cpk uses the within-subgroup (short-term) standard deviation. Long-term variation is always ≥ short-term variation, so Ppk ≤ Cpk. The ratio Cpk/Ppk is sometimes called the 'capability ratio.'

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

More Lean Six Sigma Exam Topics

Studying for the Lean Six Sigma exam? Read more about Six Sigma Green Belt Prep