Skip to main content

Contractor License Exam

Construction Law and Contracts Practice Questions

60 practice questions with detailed explanations — aligned to the Contractor License Exam.

Master Construction Law and Contracts to boost your score on the Contractor License Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 60 questions, review any that trip you up, and use the related topics below to round out your preparation.

  1. Q1.A lump-sum (fixed-price) contract means the contractor agrees to:

    A.Perform work for cost plus a percentage fee
    B.Complete the described scope of work for a fixed total price
    C.Perform work and invoice weekly for materials and labor
    D.Provide work under a time-and-materials arrangement with a ceiling
    BComplete the described scope of work for a fixed total price

    Explanation: In a lump-sum contract, the contractor agrees to complete the defined scope for a fixed total price, bearing the risk of cost overruns. Changes to scope require written change orders to adjust the contract price.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  2. Q2.A mechanic's lien gives a contractor or subcontractor the right to:

    A.Perform emergency repairs without owner consent
    B.Place a claim against the owner's property if payment is not received
    C.Stop work immediately without penalty
    D.Recover double damages in court
    BPlace a claim against the owner's property if payment is not received

    Explanation: A mechanic's lien (also called a construction lien or materialman's lien) allows unpaid contractors, subcontractors, and suppliers to place a claim against the owner's property title as security for the unpaid debt.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  3. Q3.Which document formally authorizes changes to the original contract scope, schedule, or price?

    A.Request for Information (RFI)
    B.Shop drawing
    C.Change order
    D.Notice to proceed
    CChange order

    Explanation: A change order is the formal written agreement between the owner and contractor authorizing modifications to contract scope, schedule, or price. Work outside the original contract should not proceed without an executed change order.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  4. Q4.Substantial completion in construction contracts means:

    A.The project is 50% complete
    B.The work is sufficiently complete for the owner to occupy or use it for its intended purpose
    C.All punch list items are corrected and final payment is made
    D.The contractor has submitted all close-out documents
    BThe work is sufficiently complete for the owner to occupy or use it for its intended purpose

    Explanation: Substantial completion occurs when the work is sufficiently complete for the owner to use it for its intended purpose. It typically triggers the start of the warranty period, release of retainage, and shifts responsibility for the premises to the owner.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  5. Q5.A 'notice to proceed' (NTP) is issued by:

    A.The contractor to the subcontractors
    B.The owner or owner's representative to the contractor, authorizing work to begin
    C.The building department when a permit is approved
    D.The surety company when a bond is issued
    BThe owner or owner's representative to the contractor, authorizing work to begin

    Explanation: A notice to proceed (NTP) is issued by the owner or owner's representative (often the architect/engineer) to the general contractor, formally authorizing the contractor to begin work and establishing the contract start date.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  6. Q6.Liquidated damages in a construction contract are:

    A.A penalty paid to the contractor for early completion
    B.A pre-agreed daily amount the contractor pays the owner for each day of delay beyond the contract completion date
    C.Damages assessed by a court after a lawsuit
    D.The cost of any materials that become damaged during construction
    BA pre-agreed daily amount the contractor pays the owner for each day of delay beyond the contract completion date

    Explanation: Liquidated damages are a pre-estimated, agreed-upon daily penalty that the contractor owes the owner for each day the project extends beyond the contract completion date. They must represent a reasonable estimate of actual damages, not a penalty.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  7. Q7.An indemnification (hold harmless) clause in a construction contract requires one party to:

    A.Pay the other party's health insurance premiums
    B.Protect the other party from losses or liabilities arising from the indemnifying party's work
    C.Guarantee the lowest possible contract price
    D.Complete work within a specified number of calendar days
    BProtect the other party from losses or liabilities arising from the indemnifying party's work

    Explanation: An indemnification clause requires the indemnifying party (typically the contractor or subcontractor) to protect and defend the indemnified party (typically the owner) from specified claims, losses, or liabilities arising from the indemnifying party's work or negligence.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  8. Q8.Retainage in construction contracts refers to:

    A.A deposit paid to the contractor before work begins
    B.A percentage of each payment withheld by the owner until substantial completion or final acceptance
    C.The contractor's profit margin built into the contract price
    D.Money held in escrow for material purchases
    BA percentage of each payment withheld by the owner until substantial completion or final acceptance

    Explanation: Retainage (typically 5–10% of each progress payment) is withheld by the owner as security to ensure the contractor completes all work and corrects deficiencies. It is released at substantial completion or after punch list completion.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  9. Q9.A statute of limitations in construction law sets the time period within which:

    A.A permit must be obtained after contract signing
    B.A party must file a claim or lawsuit
    C.A contractor must complete the project
    D.Subcontractors must be paid after general contractor receives payment
    BA party must file a claim or lawsuit

    Explanation: The statute of limitations establishes the maximum time a party has to file a legal claim after a cause of action arises (such as a construction defect or breach of contract). After this period, the claim is typically time-barred.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  10. Q10.A bid bond guarantees that the bidder will:

    A.Complete the project within budget
    B.Enter into the contract and provide required performance and payment bonds if awarded the project
    C.Pay all subcontractors promptly
    D.Correct any defects discovered during the warranty period
    BEnter into the contract and provide required performance and payment bonds if awarded the project

    Explanation: A bid bond guarantees that if the bidder is awarded the contract, they will sign the contract and provide the required performance and payment bonds. If the bidder refuses, the owner can claim the bond amount to cover the cost difference with the next bidder.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

More Contractor License Exam Topics

Studying for the Contractor License exam? Read more about Contractor License Prep