Contractor License Exam
Construction Law and Contracts Practice Questions
60 practice questions with detailed explanations — aligned to the Contractor License Exam.
Master Construction Law and Contracts to boost your score on the Contractor License Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 60 questions, review any that trip you up, and use the related topics below to round out your preparation.
Q1.A lump-sum (fixed-price) contract means the contractor agrees to:
A.Perform work for cost plus a percentage feeB.Complete the described scope of work for a fixed total priceC.Perform work and invoice weekly for materials and laborD.Provide work under a time-and-materials arrangement with a ceiling✓B. Complete the described scope of work for a fixed total priceExplanation: In a lump-sum contract, the contractor agrees to complete the defined scope for a fixed total price, bearing the risk of cost overruns. Changes to scope require written change orders to adjust the contract price.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q2.A mechanic's lien gives a contractor or subcontractor the right to:
A.Perform emergency repairs without owner consentB.Place a claim against the owner's property if payment is not receivedC.Stop work immediately without penaltyD.Recover double damages in court✓B. Place a claim against the owner's property if payment is not receivedExplanation: A mechanic's lien (also called a construction lien or materialman's lien) allows unpaid contractors, subcontractors, and suppliers to place a claim against the owner's property title as security for the unpaid debt.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q3.Which document formally authorizes changes to the original contract scope, schedule, or price?
A.Request for Information (RFI)B.Shop drawingC.Change orderD.Notice to proceed✓C. Change orderExplanation: A change order is the formal written agreement between the owner and contractor authorizing modifications to contract scope, schedule, or price. Work outside the original contract should not proceed without an executed change order.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q4.Substantial completion in construction contracts means:
A.The project is 50% completeB.The work is sufficiently complete for the owner to occupy or use it for its intended purposeC.All punch list items are corrected and final payment is madeD.The contractor has submitted all close-out documents✓B. The work is sufficiently complete for the owner to occupy or use it for its intended purposeExplanation: Substantial completion occurs when the work is sufficiently complete for the owner to use it for its intended purpose. It typically triggers the start of the warranty period, release of retainage, and shifts responsibility for the premises to the owner.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q5.A 'notice to proceed' (NTP) is issued by:
A.The contractor to the subcontractorsB.The owner or owner's representative to the contractor, authorizing work to beginC.The building department when a permit is approvedD.The surety company when a bond is issued✓B. The owner or owner's representative to the contractor, authorizing work to beginExplanation: A notice to proceed (NTP) is issued by the owner or owner's representative (often the architect/engineer) to the general contractor, formally authorizing the contractor to begin work and establishing the contract start date.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q6.Liquidated damages in a construction contract are:
A.A penalty paid to the contractor for early completionB.A pre-agreed daily amount the contractor pays the owner for each day of delay beyond the contract completion dateC.Damages assessed by a court after a lawsuitD.The cost of any materials that become damaged during construction✓B. A pre-agreed daily amount the contractor pays the owner for each day of delay beyond the contract completion dateExplanation: Liquidated damages are a pre-estimated, agreed-upon daily penalty that the contractor owes the owner for each day the project extends beyond the contract completion date. They must represent a reasonable estimate of actual damages, not a penalty.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q7.An indemnification (hold harmless) clause in a construction contract requires one party to:
A.Pay the other party's health insurance premiumsB.Protect the other party from losses or liabilities arising from the indemnifying party's workC.Guarantee the lowest possible contract priceD.Complete work within a specified number of calendar days✓B. Protect the other party from losses or liabilities arising from the indemnifying party's workExplanation: An indemnification clause requires the indemnifying party (typically the contractor or subcontractor) to protect and defend the indemnified party (typically the owner) from specified claims, losses, or liabilities arising from the indemnifying party's work or negligence.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q8.Retainage in construction contracts refers to:
A.A deposit paid to the contractor before work beginsB.A percentage of each payment withheld by the owner until substantial completion or final acceptanceC.The contractor's profit margin built into the contract priceD.Money held in escrow for material purchases✓B. A percentage of each payment withheld by the owner until substantial completion or final acceptanceExplanation: Retainage (typically 5–10% of each progress payment) is withheld by the owner as security to ensure the contractor completes all work and corrects deficiencies. It is released at substantial completion or after punch list completion.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q9.A statute of limitations in construction law sets the time period within which:
A.A permit must be obtained after contract signingB.A party must file a claim or lawsuitC.A contractor must complete the projectD.Subcontractors must be paid after general contractor receives payment✓B. A party must file a claim or lawsuitExplanation: The statute of limitations establishes the maximum time a party has to file a legal claim after a cause of action arises (such as a construction defect or breach of contract). After this period, the claim is typically time-barred.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q10.A bid bond guarantees that the bidder will:
A.Complete the project within budgetB.Enter into the contract and provide required performance and payment bonds if awarded the projectC.Pay all subcontractors promptlyD.Correct any defects discovered during the warranty period✓B. Enter into the contract and provide required performance and payment bonds if awarded the projectExplanation: A bid bond guarantees that if the bidder is awarded the contract, they will sign the contract and provide the required performance and payment bonds. If the bidder refuses, the owner can claim the bond amount to cover the cost difference with the next bidder.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
More Contractor License Exam Topics
Studying for the Contractor License exam? Read more about Contractor License Prep →