Contractor License Exam
Project Management and Scheduling Practice Questions
55 practice questions with detailed explanations — aligned to the Contractor License Exam.
Master Project Management and Scheduling to boost your score on the Contractor License Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 55 questions, review any that trip you up, and use the related topics below to round out your preparation.
Q1.What is the critical path in construction scheduling?
A.The most expensive sequence of activities on a projectB.The longest sequence of dependent activities that determines the minimum project durationC.Activities that are most at risk of weather delayD.The sequence of activities involving the most subcontractorsB. The longest sequence of dependent activities that determines the minimum project durationExplanation: The critical path is the longest sequence of dependent activities that determines the project's minimum duration. Any delay to a critical path activity delays the entire project. Float (slack) is zero on critical path activities. CPM (Critical Path Method) scheduling is the standard approach for managing construction timelines.
Join 1,000+ users passing the Contractor License
Q2.What is the purpose of a daily log or job site diary?
A.To track subcontractor bid pricesB.To document daily conditions, work performed, workforce count, visitors, and incidents for legal and project management purposesC.To record material delivery prices for accountingD.To track the contractor's profit margin each dayB. To document daily conditions, work performed, workforce count, visitors, and incidents for legal and project management purposesExplanation: The daily log is the contractor's contemporaneous record of job site conditions — weather, personnel on site, work performed, materials delivered, visitors, equipment used, and any incidents or delays. Daily logs are critical evidence in construction disputes and claims.
Join 1,000+ users passing the Contractor License
Q3.What is a change order in construction?
A.An order to change subcontractors during the projectB.A written amendment to the original contract scope, modifying work, cost, and/or scheduleC.A permit required when changing materials specificationsD.A punch list item requiring correction before final paymentB. A written amendment to the original contract scope, modifying work, cost, and/or scheduleExplanation: A change order is a formal written agreement between the owner and contractor that modifies the original contract by adding, deleting, or changing scope of work, contract price, and/or completion date. Change orders must be signed by authorized parties before additional work is performed to protect both parties.
Join 1,000+ users passing the Contractor License
Q4.What does 'float' mean in a construction schedule?
A.The markup percentage on labor costsB.The amount of time an activity can be delayed without delaying the project completion dateC.The contractor's contingency budget for unexpected costsD.The time allotted for material procurement before construction beginsB. The amount of time an activity can be delayed without delaying the project completion dateExplanation: Float (also called slack) is the amount of time a non-critical activity can be delayed without impacting the project's overall completion date. Activities on the critical path have zero float. Managing float allows the project manager to prioritize resources and accommodate minor delays.
Join 1,000+ users passing the Contractor License
Q5.What is a punch list in construction?
A.A list of subcontractors approved to bid on a projectB.A list of incomplete or defective work items that must be corrected before final payment and project closeoutC.A schedule of material deliveries organized by priorityD.A record of safety violations noted during inspectionB. A list of incomplete or defective work items that must be corrected before final payment and project closeoutExplanation: The punch list (also called a snag list) is a document prepared at or near substantial completion listing remaining items to be completed or corrected — minor deficiencies, cosmetic repairs, missing accessories, etc. Final payment is typically withheld until punch list items are resolved.
Join 1,000+ users passing the Contractor License