Skip to main content

PMP Project Management Professional Practice Test

50 practice questions across 5 topics, each with a written explanation of why the correct answer is correct. Start below — the first questions are free and no account is required.

Topics on the PMP Project Management Professional exam

Sample PMP Project Management Professional questions

Project Integration Management

Which document formally authorizes a project and grants the project manager authority to apply organizational resources?

  1. A. Project Management Plan
  2. B. Project Charter
  3. C. Statement of Work
  4. D. Business Case

Answer: B. The Project Charter formally authorizes the project and grants the project manager the authority to apply resources. It is issued by the sponsor and includes high-level objectives, milestones, budget, and stakeholder identification. It is the output of the Develop Project Charter process.

Scope and Schedule Management

What is the Work Breakdown Structure (WBS)?

  1. A. A list of all resources required for the project
  2. B. A hierarchical decomposition of the total scope of work to be carried out by the project team
  3. C. A Gantt chart showing the project schedule
  4. D. A list of all project risks and their probability

Answer: B. The WBS is a hierarchical decomposition of the project scope into smaller, manageable work packages. Each level represents a finer breakdown of work. The 100% rule requires that the WBS captures all project work — no more, no less.

Risk Management

What is the formula for Expected Monetary Value (EMV) used in risk analysis?

  1. A. EMV = Probability × Duration
  2. B. EMV = Probability × Impact (in currency)
  3. C. EMV = Impact ÷ Probability
  4. D. EMV = Total Budget × Risk Score

Answer: B. EMV = Probability × Impact. For example, a 30% chance of a $50,000 cost overrun has an EMV of $15,000. EMV is used in quantitative risk analysis and decision tree analysis to evaluate risk reserves and make risk-informed decisions.

Work through every topic on the PMP Project Management Professional question directory, or start the timed practice test below.

Loading questions…

PMP Project Management Professional exam — frequently asked questions

How many questions are on the PMP Project Management Professional exam?

The PMP Project Management Professional exam typically has 180. The exact count varies by state and exam version. VoltExam gives you 50 practice questions covering every topic tested.

What score do you need to pass the PMP Project Management Professional exam?

The passing score for the PMP Project Management Professional exam is typically Above target (scaled). Scoring significantly above the minimum on practice tests before exam day is strongly recommended to account for real-exam pressure.

What is the pass rate for the PMP Project Management Professional exam?

The estimated first-attempt pass rate for the PMP Project Management Professional exam is ~60%. Candidates who complete structured practice sessions with full answer explanations pass at significantly higher rates.

How long should I study for the PMP Project Management Professional exam?

Most candidates study 3–6 months for the PMP Project Management Professional exam. Study time varies based on prior experience. Focusing on practice questions with explanations is the most time-efficient preparation method.

What topics are on the PMP Project Management Professional exam?

The PMP Project Management Professional exam covers topics including: Project Integration Management, Scope and Schedule Management, Risk Management, Agile and Hybrid Frameworks, Stakeholder and Communication Management. VoltExam's free study mode organizes 50 quick-study questions by concept so you can target weak areas efficiently.