PMI lists 180 questions, including 10 unscored pretest questions, in 240 minutes. The current domain weights are People 33%, Process 41%, and Business Environment 26%. PMI does not publish a fixed percentage pass line in the public outline, so this mixed practice does not produce an official pass prediction or PMI training-hour credit.
50 public supplemental prompts across 5 topics, each with a written explanation of why the correct answer is correct. Start below — the first questions are free and no account is required.
Sample supplemental PMP Project Management Professional questions
Project Integration Management
Which document formally authorizes a project and grants the project manager authority to apply organizational resources?
A. Project Management Plan
B. Statement of Work
C. Project Charter
D. Business Case
Answer: C. The Project Charter formally authorizes the project and grants the project manager the authority to apply resources. It is issued by the sponsor and includes high-level objectives, milestones, budget, and stakeholder identification. It is the output of the Develop Project Charter process.
Scope and Schedule Management
What is the Work Breakdown Structure (WBS)?
A. A Gantt chart showing the project schedule
B. A list of all resources required for the project
C. A hierarchical decomposition of the total scope of work to be carried out by the project team
D. A list of all project risks and their probability
Answer: C. The WBS is a hierarchical decomposition of the project scope into smaller, manageable work packages. Each level represents a finer breakdown of work. The 100% rule requires that the WBS captures all project work — no more, no less.
Risk Management
What is the formula for Expected Monetary Value (EMV) used in risk analysis?
A. EMV = Total Budget × Risk Score
B. EMV = Impact ÷ Probability
C. EMV = Probability × Duration
D. EMV = Probability × Impact (in currency)
Answer: D. EMV = Probability × Impact. For example, a 30% chance of a $50,000 cost overrun has an EMV of $15,000. EMV is used in quantitative risk analysis and decision tree analysis to evaluate risk reserves and make risk-informed decisions.
PMP Project Management Professional exam — frequently asked questions
How many questions are on the PMP Project Management Professional exam?
PMI's July 2026 outline lists 180 questions in 240 minutes: 170 scored and 10 unscored pretest questions, with two 10-minute breaks. VoltExam provides 165 distinct questions in the paid web bank; the public quick-study directory contains 50 questions for supplemental practice.
What score do you need to pass the PMP Project Management Professional exam?
PMI does not publish a fixed percentage passing score in the July 2026 public Examination Content Outline. Use practice results to choose review topics, not as an official pass prediction.
What is the pass rate for the PMP Project Management Professional exam?
PMI does not publish a first-attempt pass-rate percentage in the July 2026 public Examination Content Outline, so VoltExam does not estimate one or claim that practice predicts the certification result.
How long should I study for the PMP Project Management Professional exam?
PMI requires 35 hours of qualifying project-management training but does not prescribe one additional self-study duration in the July 2026 public outline. VoltExam practice is supplemental and does not provide PMI training-hour credit.
What topics are on the PMP Project Management Professional exam?
PMI's July 2026 outline weights People at 33%, Process at 41%, and Business Environment at 26%. Approximately 40% of items use predictive approaches, while the remaining 60% is divided between adaptive/agile and hybrid approaches. VoltExam provides 165 distinct questions in the paid web bank; the public quick-study directory contains 50 questions for supplemental review.