PMP Project Management Professional Exam

Agile and Hybrid Frameworks Practice Questions

60 practice questions with detailed explanations — aligned to the PMP Project Management Professional Exam.

Master Agile and Hybrid Frameworks to boost your score on the PMP Project Management Professional Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 60 questions, review any that trip you up, and use the related topics below to round out your preparation.

  1. Q1.What are the four values in the Agile Manifesto?

    A.Processes, tools, documentation, and plans
    B.Individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a plan
    C.Scope, cost, schedule, and quality
    D.Velocity, burn-down, retrospectives, and reviews
    BIndividuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a plan

    Explanation: The Agile Manifesto (2001) states four core values: Individuals and interactions OVER processes and tools; Working software OVER comprehensive documentation; Customer collaboration OVER contract negotiation; Responding to change OVER following a plan. The 'over' means the right side has value — the left is just valued more.

    Join 1,000+ users passing the PMP Project Management Professional

  2. Q2.In Scrum, who is responsible for maximizing the value of the product and managing the product backlog?

    A.Scrum Master
    B.Development Team
    C.Product Owner
    D.Project Sponsor
    CProduct Owner

    Explanation: The Product Owner owns and prioritizes the product backlog, ensuring it reflects stakeholder value. The Scrum Master facilitates Scrum events and removes impediments. The Development Team self-organizes to complete sprint work. The sponsor is outside the Scrum team.

    Join 1,000+ users passing the PMP Project Management Professional

  3. Q3.What is velocity in an agile project?

    A.The speed at which team members complete individual tasks
    B.The number of story points (or backlog items) completed per sprint — used to forecast future capacity
    C.The rate at which new backlog items are added
    D.The percentage of the product backlog completed to date
    BThe number of story points (or backlog items) completed per sprint — used to forecast future capacity

    Explanation: Velocity is the amount of work (measured in story points, story count, or other units) completed by the team in a sprint. It is used to forecast how much work the team can complete in future sprints and to predict the release date.

    Join 1,000+ users passing the PMP Project Management Professional

  4. Q4.When is a hybrid project management approach most appropriate?

    A.When the project has zero uncertainty and fully defined requirements
    B.When some project components have well-defined requirements and others need flexibility and iteration
    C.When stakeholders refuse to participate in the agile process
    D.Only for IT projects — not construction or manufacturing
    BWhen some project components have well-defined requirements and others need flexibility and iteration

    Explanation: A hybrid approach combines predictive (waterfall) and agile elements. It works well when some deliverables have stable requirements (planned predictively) while others involve innovation or uncertainty (handled iteratively). For example, regulatory compliance may be predictive while product features are developed agile.

    Join 1,000+ users passing the PMP Project Management Professional

  5. Q5.What is the Definition of Done (DoD) in Scrum?

    A.The list of tasks remaining in the current sprint
    B.A shared understanding of what it means for a product backlog item to be complete — the criteria that must be met before work is accepted
    C.The project's final deliverable acceptance criteria from the sponsor
    D.The sprint goal established at the sprint planning meeting
    BA shared understanding of what it means for a product backlog item to be complete — the criteria that must be met before work is accepted

    Explanation: The Definition of Done is a shared, formal list of criteria that a product increment must meet before it is considered done. It promotes transparency and ensures the team has a consistent understanding of quality. Items not meeting the DoD cannot be 'accepted' in the sprint review.

    Join 1,000+ users passing the PMP Project Management Professional

Want all 300 questions?

Download VoltExam — $99.99 Lifetime

Offline access, 300+ questions, built-in calculators. One-time unlock, no subscription.

Download on the App Store

More PMP Project Management Professional Exam Topics