PMP Project Management Professional Exam
Agile and Hybrid Frameworks Practice Questions
10 practice questions with detailed explanations — aligned to the PMP Project Management Professional Exam.
Master Agile and Hybrid Frameworks to boost your score on the PMP Project Management Professional Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 10 questions, review any that trip you up, and use the related topics below to round out your preparation.
Q1.What are the four values in the Agile Manifesto?
A.Processes, tools, documentation, and plansB.Individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a planC.Scope, cost, schedule, and qualityD.Velocity, burn-down, retrospectives, and reviews✓B. Individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a planExplanation: The Agile Manifesto (2001) states four core values: Individuals and interactions OVER processes and tools; Working software OVER comprehensive documentation; Customer collaboration OVER contract negotiation; Responding to change OVER following a plan. The 'over' means the right side has value — the left is just valued more.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q2.In Scrum, who is responsible for maximizing the value of the product and managing the product backlog?
A.Scrum MasterB.Development TeamC.Product OwnerD.Project Sponsor✓C. Product OwnerExplanation: The Product Owner owns and prioritizes the product backlog, ensuring it reflects stakeholder value. The Scrum Master facilitates Scrum events and removes impediments. The Development Team self-organizes to complete sprint work. The sponsor is outside the Scrum team.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q3.What is velocity in an agile project?
A.The speed at which team members complete individual tasksB.The number of story points (or backlog items) completed per sprint — used to forecast future capacityC.The rate at which new backlog items are addedD.The percentage of the product backlog completed to date✓B. The number of story points (or backlog items) completed per sprint — used to forecast future capacityExplanation: Velocity is the amount of work (measured in story points, story count, or other units) completed by the team in a sprint. It is used to forecast how much work the team can complete in future sprints and to predict the release date.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q4.When is a hybrid project management approach most appropriate?
A.When the project has zero uncertainty and fully defined requirementsB.When some project components have well-defined requirements and others need flexibility and iterationC.When stakeholders refuse to participate in the agile processD.Only for IT projects — not construction or manufacturing✓B. When some project components have well-defined requirements and others need flexibility and iterationExplanation: A hybrid approach combines predictive (waterfall) and agile elements. It works well when some deliverables have stable requirements (planned predictively) while others involve innovation or uncertainty (handled iteratively). For example, regulatory compliance may be predictive while product features are developed agile.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q5.What is the Definition of Done (DoD) in Scrum?
A.The list of tasks remaining in the current sprintB.A shared understanding of what it means for a product backlog item to be complete — the criteria that must be met before work is acceptedC.The project's final deliverable acceptance criteria from the sponsorD.The sprint goal established at the sprint planning meeting✓B. A shared understanding of what it means for a product backlog item to be complete — the criteria that must be met before work is acceptedExplanation: The Definition of Done is a shared, formal list of criteria that a product increment must meet before it is considered done. It promotes transparency and ensures the team has a consistent understanding of quality. Items not meeting the DoD cannot be 'accepted' in the sprint review.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q6.In Scrum, what is the purpose of the Sprint Retrospective?
A.For the team to inspect its own process and identify improvements for the next SprintB.For the Product Owner to reprioritize the Product BacklogC.For stakeholders to review and accept the Sprint incrementD.For the Scrum Master to assign tasks for the next Sprint✓A. For the team to inspect its own process and identify improvements for the next SprintExplanation: The Sprint Retrospective is a time-boxed event at the end of each Sprint where the Scrum Team reflects on how they worked together — what went well, what didn't, and what to improve. It focuses on the team's process, not the product (which is the Sprint Review's focus).
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q7.The Agile Manifesto values 'Responding to change over following a plan.' How does this apply to project management?
A.Teams should adapt the plan when new information or changing requirements provide more value than strict adherenceB.Plans should be abandoned entirely in favor of day-to-day improvisationC.Change requests are always accepted without review in Agile projectsD.Customer requirements are fixed at the start and changes are avoided✓A. Teams should adapt the plan when new information or changing requirements provide more value than strict adherenceExplanation: The Agile Manifesto does not reject planning — it values the ability to respond to change when circumstances evolve. Agile teams use iterative cycles (sprints/iterations) to regularly inspect and adapt. Planning still occurs but is continuous and lightweight rather than fully front-loaded.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q8.A hybrid project uses waterfall for regulatory compliance phases and Agile for development sprints. What is the main benefit of a hybrid approach?
A.Combines the predictability of plan-driven methods with the flexibility of iterative methods to suit different project phasesB.Eliminates all risk by using two project management frameworks simultaneouslyC.Reduces team size by combining two teams into oneD.Satisfies both PMI and Scrum Alliance certification requirements✓A. Combines the predictability of plan-driven methods with the flexibility of iterative methods to suit different project phasesExplanation: Hybrid project management applies predictive (waterfall) methods where requirements are stable and regulatory compliance demands fixed documentation, while applying adaptive (Agile) methods where innovation, iteration, and customer feedback add value. The approach is tailored to the project's needs.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q9.In a Kanban system, Work in Progress (WIP) limits are used to:
A.Prevent bottlenecks by limiting how much work can be in each stage simultaneouslyB.Restrict the total number of backlog items the team can planC.Limit the number of team members who can work on a single taskD.Ensure each sprint has no more than 10 user stories✓A. Prevent bottlenecks by limiting how much work can be in each stage simultaneouslyExplanation: WIP limits in Kanban constrain the number of work items in each workflow stage (e.g., In Progress, Testing) to reduce multitasking, expose bottlenecks, and improve flow. When a column hits its WIP limit, the team must complete existing work before pulling new work in.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q10.The Agile concept of 'Definition of Done' (DoD) establishes:
A.A shared team agreement on the criteria a backlog item must meet to be considered completeB.The project sponsor's acceptance criteria for the final productC.The Scrum Master's checklist for Sprint planningD.The minimum viable product (MVP) requirements for customer delivery✓A. A shared team agreement on the criteria a backlog item must meet to be considered completeExplanation: The Definition of Done is a team-created checklist of quality criteria (e.g., code written, reviewed, tested, documented, deployed) that every Product Backlog Item must meet before it can be called 'Done.' It ensures consistent quality and transparency about what 'complete' means.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
More PMP Project Management Professional Exam Topics
Studying for the PMP Project Management Professional exam? Read more about PMP Prep: Project Management →