PMP Project Management Professional Exam
Project Integration Management Practice Questions
10 practice questions with detailed explanations — aligned to the PMP Project Management Professional Exam.
Master Project Integration Management to boost your score on the PMP Project Management Professional Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 10 questions, review any that trip you up, and use the related topics below to round out your preparation.
Q1.Which document formally authorizes a project and grants the project manager authority to apply organizational resources?
A.Project Management PlanB.Project CharterC.Statement of WorkD.Business Case✓B. Project CharterExplanation: The Project Charter formally authorizes the project and grants the project manager the authority to apply resources. It is issued by the sponsor and includes high-level objectives, milestones, budget, and stakeholder identification. It is the output of the Develop Project Charter process.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q2.A project manager learns that a major scope change is needed. What should they do FIRST?
A.Implement the change immediately to avoid delaysB.Notify only the sponsor and proceedC.Submit the change through the Perform Integrated Change Control processD.Reject the change to protect the original scope✓C. Submit the change through the Perform Integrated Change Control processExplanation: All changes — scope, schedule, cost, or quality — must go through the Perform Integrated Change Control process. This ensures changes are evaluated for impact on all project constraints before approval. Implementing changes without approval violates project governance.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q3.What is the primary purpose of lessons learned in project management?
A.To document team performance for HR reviewsB.To capture project knowledge for use in current and future projectsC.To justify cost overruns to stakeholdersD.To identify who was responsible for project issues✓B. To capture project knowledge for use in current and future projectsExplanation: Lessons learned (organizational process assets) are documented throughout the project and at close-out to capture what worked, what didn't, and recommendations for future projects. They are stored in the lessons learned repository for use on future projects.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q4.In an agile project, what document serves a similar function to the project charter?
A.Sprint BacklogB.Product Vision Statement and Project CanvasC.Velocity ChartD.Definition of Done✓B. Product Vision Statement and Project CanvasExplanation: In agile projects, a Product Vision Statement or Project Canvas (e.g., Lean Project Canvas) captures the high-level purpose, stakeholders, and outcomes — serving a similar authorization function as the project charter without the detailed planning of a traditional charter.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q5.Which process group occurs when a project is officially closed?
A.InitiatingB.PlanningC.Monitoring and ControllingD.Closing✓D. ClosingExplanation: The Closing process group finalizes all activities across all process groups to formally close the project or phase. Activities include final deliverable acceptance, releasing resources, archiving records, and documenting lessons learned.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q6.A project manager is asked to authorize a new project and formally establish its existence. Which document accomplishes this?
A.Project charterB.Project management planC.Business caseD.Statement of work (SOW)✓A. Project charterExplanation: The project charter formally authorizes the project's existence, grants the project manager authority to apply resources, and documents high-level scope, objectives, and stakeholders. It is created during the Initiating process group — the first formal project document.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q7.Integrated change control (ICC) ensures that changes to a project go through what process?
A.A formal review and approval before being incorporated into the project baselineB.Immediate implementation to avoid schedule delaysC.Approval by the project team only, not the sponsorD.Documentation after implementation to maintain an audit trail✓A. A formal review and approval before being incorporated into the project baselineExplanation: Integrated change control requires all change requests to be reviewed, evaluated for impact, and formally approved or rejected before changes are made to the baseline. ICC prevents scope creep and ensures all baselines (scope, schedule, cost) remain controlled.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q8.Which document describes how the project will be planned, executed, monitored, and closed — serving as the master plan for the project?
A.Project management planB.Project charterC.Work breakdown structure (WBS)D.Change management plan✓A. Project management planExplanation: The project management plan is the comprehensive document that defines how the project will be executed, monitored, and controlled. It includes subsidiary plans (scope, schedule, cost, quality, communication, risk, procurement, stakeholder management) and all baseline documents.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q9.During project closure, the project manager must conduct a lessons learned session. What is the primary purpose of documenting lessons learned?
A.To improve future project performance by sharing knowledge gained during the current projectB.To identify who was responsible for project problemsC.To satisfy contractual requirements for client deliverable acceptanceD.To calculate the final project cost variance✓A. To improve future project performance by sharing knowledge gained during the current projectExplanation: Lessons learned documentation captures what went well, what went poorly, and what to do differently — contributing to organizational process assets (OPAs). This knowledge is then available for future project teams, improving planning and execution across the organization.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
Q10.The Develop Project Charter process requires inputs from which of the following?
A.Business documents (business case, benefits management plan) and agreements (contracts, MOUs)B.Project schedule and cost baseline onlyC.Work breakdown structure and activity listD.Final stakeholder register and communications plan✓A. Business documents (business case, benefits management plan) and agreements (contracts, MOUs)Explanation: Per PMBOK, Develop Project Charter inputs include: business documents (business case, benefits management plan), agreements (contracts, MOUs for external projects), enterprise environmental factors (EEF), and organizational process assets (OPA). The charter itself then becomes an input to subsequent planning processes.
See answer — start free trial3-day free trial · $9.99/mo after · cancel anytime
More PMP Project Management Professional Exam Topics
Studying for the PMP Project Management Professional exam? Read more about PMP Prep: Project Management →