PMP Project Management Professional Exam

Project Integration Management Practice Questions

60 practice questions with detailed explanations — aligned to the PMP Project Management Professional Exam.

Master Project Integration Management to boost your score on the PMP Project Management Professional Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 60 questions, review any that trip you up, and use the related topics below to round out your preparation.

  1. Q1.Which document formally authorizes a project and grants the project manager authority to apply organizational resources?

    A.Project Management Plan
    B.Project Charter
    C.Statement of Work
    D.Business Case
    BProject Charter

    Explanation: The Project Charter formally authorizes the project and grants the project manager the authority to apply resources. It is issued by the sponsor and includes high-level objectives, milestones, budget, and stakeholder identification. It is the output of the Develop Project Charter process.

    Join 1,000+ users passing the PMP Project Management Professional

  2. Q2.A project manager learns that a major scope change is needed. What should they do FIRST?

    A.Implement the change immediately to avoid delays
    B.Notify only the sponsor and proceed
    C.Submit the change through the Perform Integrated Change Control process
    D.Reject the change to protect the original scope
    CSubmit the change through the Perform Integrated Change Control process

    Explanation: All changes — scope, schedule, cost, or quality — must go through the Perform Integrated Change Control process. This ensures changes are evaluated for impact on all project constraints before approval. Implementing changes without approval violates project governance.

    Join 1,000+ users passing the PMP Project Management Professional

  3. Q3.What is the primary purpose of lessons learned in project management?

    A.To document team performance for HR reviews
    B.To capture project knowledge for use in current and future projects
    C.To justify cost overruns to stakeholders
    D.To identify who was responsible for project issues
    BTo capture project knowledge for use in current and future projects

    Explanation: Lessons learned (organizational process assets) are documented throughout the project and at close-out to capture what worked, what didn't, and recommendations for future projects. They are stored in the lessons learned repository for use on future projects.

    Join 1,000+ users passing the PMP Project Management Professional

  4. Q4.In an agile project, what document serves a similar function to the project charter?

    A.Sprint Backlog
    B.Product Vision Statement and Project Canvas
    C.Velocity Chart
    D.Definition of Done
    BProduct Vision Statement and Project Canvas

    Explanation: In agile projects, a Product Vision Statement or Project Canvas (e.g., Lean Project Canvas) captures the high-level purpose, stakeholders, and outcomes — serving a similar authorization function as the project charter without the detailed planning of a traditional charter.

    Join 1,000+ users passing the PMP Project Management Professional

  5. Q5.Which process group occurs when a project is officially closed?

    A.Initiating
    B.Planning
    C.Monitoring and Controlling
    D.Closing
    DClosing

    Explanation: The Closing process group finalizes all activities across all process groups to formally close the project or phase. Activities include final deliverable acceptance, releasing resources, archiving records, and documenting lessons learned.

    Join 1,000+ users passing the PMP Project Management Professional

Want all 300 questions?

Download VoltExam — $99.99 Lifetime

Offline access, 300+ questions, built-in calculators. One-time unlock, no subscription.

Download on the App Store

More PMP Project Management Professional Exam Topics