Skip to main content

PMP Project Management Professional Exam

Project Integration Management Practice Questions

10 practice questions with detailed explanations — aligned to the PMP Project Management Professional Exam.

Master Project Integration Management to boost your score on the PMP Project Management Professional Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 10 questions, review any that trip you up, and use the related topics below to round out your preparation.

  1. Q1.Which document formally authorizes a project and grants the project manager authority to apply organizational resources?

    A.Project Management Plan
    B.Project Charter
    C.Statement of Work
    D.Business Case
    BProject Charter

    Explanation: The Project Charter formally authorizes the project and grants the project manager the authority to apply resources. It is issued by the sponsor and includes high-level objectives, milestones, budget, and stakeholder identification. It is the output of the Develop Project Charter process.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  2. Q2.A project manager learns that a major scope change is needed. What should they do FIRST?

    A.Implement the change immediately to avoid delays
    B.Notify only the sponsor and proceed
    C.Submit the change through the Perform Integrated Change Control process
    D.Reject the change to protect the original scope
    CSubmit the change through the Perform Integrated Change Control process

    Explanation: All changes — scope, schedule, cost, or quality — must go through the Perform Integrated Change Control process. This ensures changes are evaluated for impact on all project constraints before approval. Implementing changes without approval violates project governance.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  3. Q3.What is the primary purpose of lessons learned in project management?

    A.To document team performance for HR reviews
    B.To capture project knowledge for use in current and future projects
    C.To justify cost overruns to stakeholders
    D.To identify who was responsible for project issues
    BTo capture project knowledge for use in current and future projects

    Explanation: Lessons learned (organizational process assets) are documented throughout the project and at close-out to capture what worked, what didn't, and recommendations for future projects. They are stored in the lessons learned repository for use on future projects.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  4. Q4.In an agile project, what document serves a similar function to the project charter?

    A.Sprint Backlog
    B.Product Vision Statement and Project Canvas
    C.Velocity Chart
    D.Definition of Done
    BProduct Vision Statement and Project Canvas

    Explanation: In agile projects, a Product Vision Statement or Project Canvas (e.g., Lean Project Canvas) captures the high-level purpose, stakeholders, and outcomes — serving a similar authorization function as the project charter without the detailed planning of a traditional charter.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  5. Q5.Which process group occurs when a project is officially closed?

    A.Initiating
    B.Planning
    C.Monitoring and Controlling
    D.Closing
    DClosing

    Explanation: The Closing process group finalizes all activities across all process groups to formally close the project or phase. Activities include final deliverable acceptance, releasing resources, archiving records, and documenting lessons learned.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  6. Q6.A project manager is asked to authorize a new project and formally establish its existence. Which document accomplishes this?

    A.Project charter
    B.Project management plan
    C.Business case
    D.Statement of work (SOW)
    AProject charter

    Explanation: The project charter formally authorizes the project's existence, grants the project manager authority to apply resources, and documents high-level scope, objectives, and stakeholders. It is created during the Initiating process group — the first formal project document.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  7. Q7.Integrated change control (ICC) ensures that changes to a project go through what process?

    A.A formal review and approval before being incorporated into the project baseline
    B.Immediate implementation to avoid schedule delays
    C.Approval by the project team only, not the sponsor
    D.Documentation after implementation to maintain an audit trail
    AA formal review and approval before being incorporated into the project baseline

    Explanation: Integrated change control requires all change requests to be reviewed, evaluated for impact, and formally approved or rejected before changes are made to the baseline. ICC prevents scope creep and ensures all baselines (scope, schedule, cost) remain controlled.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  8. Q8.Which document describes how the project will be planned, executed, monitored, and closed — serving as the master plan for the project?

    A.Project management plan
    B.Project charter
    C.Work breakdown structure (WBS)
    D.Change management plan
    AProject management plan

    Explanation: The project management plan is the comprehensive document that defines how the project will be executed, monitored, and controlled. It includes subsidiary plans (scope, schedule, cost, quality, communication, risk, procurement, stakeholder management) and all baseline documents.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  9. Q9.During project closure, the project manager must conduct a lessons learned session. What is the primary purpose of documenting lessons learned?

    A.To improve future project performance by sharing knowledge gained during the current project
    B.To identify who was responsible for project problems
    C.To satisfy contractual requirements for client deliverable acceptance
    D.To calculate the final project cost variance
    ATo improve future project performance by sharing knowledge gained during the current project

    Explanation: Lessons learned documentation captures what went well, what went poorly, and what to do differently — contributing to organizational process assets (OPAs). This knowledge is then available for future project teams, improving planning and execution across the organization.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  10. Q10.The Develop Project Charter process requires inputs from which of the following?

    A.Business documents (business case, benefits management plan) and agreements (contracts, MOUs)
    B.Project schedule and cost baseline only
    C.Work breakdown structure and activity list
    D.Final stakeholder register and communications plan
    ABusiness documents (business case, benefits management plan) and agreements (contracts, MOUs)

    Explanation: Per PMBOK, Develop Project Charter inputs include: business documents (business case, benefits management plan), agreements (contracts, MOUs for external projects), enterprise environmental factors (EEF), and organizational process assets (OPA). The charter itself then becomes an input to subsequent planning processes.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

More PMP Project Management Professional Exam Topics

Studying for the PMP Project Management Professional exam? Read more about PMP Prep: Project Management