Skip to main content

PMP Project Management Professional Exam

Scope and Schedule Management Practice Questions

10 practice questions with detailed explanations — aligned to the PMP Project Management Professional Exam.

Master Scope and Schedule Management to boost your score on the PMP Project Management Professional Exam. Each question below mirrors the style and difficulty of real exam questions, complete with detailed explanations so you understand the why behind every answer. Work through all 10 questions, review any that trip you up, and use the related topics below to round out your preparation.

  1. Q1.What is the Work Breakdown Structure (WBS)?

    A.A list of all resources required for the project
    B.A hierarchical decomposition of the total scope of work to be carried out by the project team
    C.A Gantt chart showing the project schedule
    D.A list of all project risks and their probability
    BA hierarchical decomposition of the total scope of work to be carried out by the project team

    Explanation: The WBS is a hierarchical decomposition of the project scope into smaller, manageable work packages. Each level represents a finer breakdown of work. The 100% rule requires that the WBS captures all project work — no more, no less.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  2. Q2.What is the critical path in a project schedule?

    A.The most expensive sequence of tasks in the project
    B.The longest path through the project network, determining the project's minimum duration
    C.The sequence of tasks most at risk of delay
    D.The path with the most parallel activities
    BThe longest path through the project network, determining the project's minimum duration

    Explanation: The critical path is the longest sequence of dependent tasks from project start to finish. Tasks on the critical path have zero float — any delay directly delays the project end date. Identifying and managing the critical path is essential to meeting the project deadline.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  3. Q3.An activity has an Early Start (ES) of day 5, Early Finish (EF) of day 9, Late Start (LS) of day 8, and Late Finish (LF) of day 12. What is the float?

    A.0 days
    B.3 days
    C.4 days
    D.7 days
    B3 days

    Explanation: Float = LS - ES = 8 - 5 = 3 days (or LF - EF = 12 - 9 = 3 days). Float represents the amount of time an activity can be delayed without delaying the project end date. Activities on the critical path have 0 float.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  4. Q4.In agile, what is the purpose of a sprint retrospective?

    A.To plan the next sprint's backlog items
    B.To demonstrate completed work to stakeholders
    C.To inspect team processes and identify improvements for the next sprint
    D.To update the product backlog with new items
    CTo inspect team processes and identify improvements for the next sprint

    Explanation: The sprint retrospective is an internal team meeting to inspect how the last sprint went (processes, tools, collaboration) and create a plan for improvements. The sprint review (demo) presents completed work to stakeholders. Sprint planning selects backlog items for the next sprint.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  5. Q5.What is scope creep?

    A.The planned gradual expansion of project scope over time
    B.Uncontrolled changes or continuous growth in project scope without corresponding adjustment to time, cost, and resources
    C.Scope reduction approved by the change control board
    D.The process of refining scope estimates at the start of each phase
    BUncontrolled changes or continuous growth in project scope without corresponding adjustment to time, cost, and resources

    Explanation: Scope creep is the unauthorized, uncontrolled expansion of project scope — adding features or work without formal change control. It is one of the most common causes of project failure. Prevention requires a clearly defined scope baseline and a robust change control process.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  6. Q6.The 100% rule in WBS development states that:

    A.The WBS must capture 100% of the work defined in the project scope — no more, no less
    B.Each work package must be completable in 100 hours or less
    C.100% of team members must review the WBS before baselined
    D.The WBS must include 100% of the project's cost in the lowest level
    AThe WBS must capture 100% of the work defined in the project scope — no more, no less

    Explanation: The 100% rule means the WBS must include ALL the work defined in the project scope statement — and only that work. Work packages not in the WBS are not authorized project work (preventing scope creep), and missing work creates schedule and cost risk.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  7. Q7.Three-point estimating uses optimistic (O), most likely (M), and pessimistic (P) estimates. In PERT (Program Evaluation and Review Technique), the weighted average is calculated as:

    A.(O + 4M + P) / 6
    B.(O + M + P) / 3
    C.(O + 2M + P) / 4
    D.(O + M + P) / 6
    A(O + 4M + P) / 6

    Explanation: The PERT formula weights the most likely estimate four times: (O + 4M + P) / 6. This gives greater weight to the realistic estimate while accounting for extreme scenarios. The simple average (O + M + P) / 3 is used in triangular distribution estimation.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  8. Q8.A project manager compresses the schedule by adding resources to critical path activities to reduce duration. This technique is called:

    A.Crashing
    B.Fast tracking
    C.Resource leveling
    D.Schedule compression analysis
    ACrashing

    Explanation: Crashing adds resources (overtime, additional staff, equipment) to critical path activities to shorten their duration — at increased cost. Fast tracking overlaps activities that would normally be sequential. Resource leveling adjusts resource assignments to resolve over-allocation, often extending the schedule.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  9. Q9.Scope creep is best prevented by:

    A.A formal change control process combined with a clearly defined scope baseline
    B.Frequent team meetings to discuss client requests
    C.Limiting stakeholder access to the project team
    D.Using an agile approach with flexible scope
    AA formal change control process combined with a clearly defined scope baseline

    Explanation: Scope creep — unauthorized or uncontrolled scope expansion — is prevented by a well-defined scope baseline (scope statement, WBS, WBS dictionary) and a formal integrated change control process that evaluates and approves all scope changes before work begins.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

  10. Q10.Which scheduling tool shows the dependencies between activities as a network diagram with nodes representing activities?

    A.Precedence Diagramming Method (PDM) — Activity-on-Node (AON)
    B.Gantt chart
    C.Milestone chart
    D.Resource breakdown structure (RBS)
    APrecedence Diagramming Method (PDM) — Activity-on-Node (AON)

    Explanation: The Precedence Diagramming Method (PDM), also called Activity-on-Node (AON), represents activities as boxes (nodes) connected by arrows showing logical dependencies (FS, FF, SS, SF). It is the foundation for calculating the critical path and schedule network analysis.

    See answer — start free trial

    3-day free trial · $9.99/mo after · cancel anytime

More PMP Project Management Professional Exam Topics

Studying for the PMP Project Management Professional exam? Read more about PMP Prep: Project Management